HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
180 units
Unit mix
176 × 2 BHK · 2 × 1 BHK · 2 × SHOP
Carpet area
35–77 sq mper unit, as filed
Floors
14
Blocks
2
Land area
7,238 sq m

Timeline

Project startedMay 2015
RERA registeredAug 2017
Proposed completionApr 2023
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

180 units across 33 batches
BuildingFloorTypeArea sq mCount
DGF2 BHK752
DGF2 BHK708
D11 BHK482
D12 BHK672
D12 BHK708
D22 BHK634
D22 BHK708
D32 BHK634
D32 BHK708
D42 BHK634
D42 BHK708
D52 BHK634
D52 BHK708
D62 BHK634
D62 BHK708
D72 BHK634
D72 BHK708
D82 BHK634
D82 BHK708
D92 BHK634
D92 BHK708
D102 BHK634
D102 BHK708
D112 BHK634
D112 BHK708
D122 BHK634
D122 BHK708
D132 BHK634
D132 BHK708
D142 BHK684
D142 BHK704
D142 BHK774
ShopGFSHOP352

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

OMAXE PANCHAM REALCON PVT. LTD. (FOMERLY PANCHAM REALCON PVT. LTD.)

CompanyPromoter type
11Registered projects
8Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,409 homeson the public record across 8 projects
82,678 sq mland declared
₹272.45 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Prayagraj
Tehsil
Karchhana
Site access
18 M wide road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 735m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.2 km · Mirzapur RoadRailway line 1.9 kmRailway station 2.7km away (Allahabad Chheoki Junction)Limited bus connectivity nearby
Water & environment
River 2.4 km · Ganges
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹41.00 Cr declared to build 180 flats. What that works out to:

₹22.78 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 13 May 2015 · 11 yrs ago
Building Permit no. 05/PR.A.(T.S.-2)/Zone-4/GH/2014-15

The promised possession date (18 Apr 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 25 Jun 2024)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan 05/PR.A.(T.S.-2)/Zone-4/GH/2014-15 on the approving authority’s portal to confirm the sanction.

Complaints register

4 complaints on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.