HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
5 × 2BHK, 5 × 3BHK
Saleable area
105–124 sq mper unit, as filed
Floors
5
Land area
446 sq m
Built-up area
1,235 sq m

Timeline

RERA approvedFeb 2024
Proposed completionFeb 2027
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
ONELLAS LAKSHMI ABODE12BHKmortgaged1051 of 1
ONELLAS LAKSHMI ABODE13BHKmortgaged1241 of 1
ONELLAS LAKSHMI ABODE22BHK1051 of 1
ONELLAS LAKSHMI ABODE23BHK1241 of 1
ONELLAS LAKSHMI ABODE32BHK1051 of 1
ONELLAS LAKSHMI ABODE33BHK1241 of 1
ONELLAS LAKSHMI ABODE42BHK1051 of 1
ONELLAS LAKSHMI ABODE43BHK1241 of 1
ONELLAS LAKSHMI ABODE52BHK1051 of 1
ONELLAS LAKSHMI ABODE53BHK1241 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ONELLA CONSTRUCTIONS

PartnershipPromoter type
Hyderabad, TelanganaBased in
2Projects
2Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
20 homeson the public record across 2 projects
2,577 sq mbuilt-up filed
862 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 2 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Road No 2, Rock Town Colony
Village
Saroornagar
Mandal
Saroornagar
District
Ranga Reddy
Pincode
500035
North boundary
PLOT NO 50 and 51
East boundary
PLOT NO 45
South boundary
40 FEET WIDE ROAD
West boundary
PLOT NO 48
What’s nearby
Schools1 school within 1km
HealthcareHospital 287m away · Clinic within 2km
LifestylePark 1.9km away · Gym or sports centre 266m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 763m away · Mall 1.5km away · Bank 368m away
Getting around
Expressway 197 m · Inner Ring RoadPrimary road 1.4 km · Inner Ring RoadRailway line 2.2 km · chaitanyapuri metroMetro station 1.6km away (Victoria Memorial)2 bus stops within 500m
Water & environment
Water body 782 m · mansoorabd
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 5635/GHMC/LBN/2024-BPSurvey no. 13 (12 to 16)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 5635/GHMC/LBN/2024-BP on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.