HORIZONMarkets
01

Complete project overview

WBRERA · Registration filing
Apartments
6
Land area
245 sq m
Built-up area
417 sq m
Carpet area
258 sq m
Parking
3 spaces
RERA registered
2025

Timeline

RERA registeredJan 2025
Proposed completionJul 2029
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

PARICHAY CONSTRUCTION

Partnership FirmPromoter type
Kolkata, West BengalBased in
2Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
14 homeson the public record across 2 projects
984 sq mbuilt-up filed
475 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
Kolkata
Police station
Survey Park
Address
MOUZA-SANTOSHPUR, J.L. NO-22, DAG NO-201, 202 & 203, KHATIAN NO-219, PREMISES NO-39, LAKE TERRACE, WARD NO-103, BOROUGH NO-XI,
Pincode
700075
What’s nearby
SchoolsNearest school 1.9km away · College or university 1.1km away · Library 827m away
HealthcareHospital 519m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 1.5km away · Bank 585m away
Getting around
Primary road 319 m · Eastern Metropolitan BypassRailway line 1.2 km · Sealdah-NamkhanaMetro station 662m away (Jyotirindra Nandi)8 bus stops within 500m
Water & environment
Water body 202 mCanal 361 m · Panchanangram Canal
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kolkata Municipal Corporation

Municipal Corporation
Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kolkata Municipal Corporation

Municipal corporation / municipality

Has approved 1,030 RERA projectsabout 1 in 2 in West Bengal, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
776
On record
14,568 flats · 0 plots
Reach
5 districts

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.