HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
40 units
Unit mix
25 × 2BHK, 15 × 3BHK
Saleable area
115–159 sq mper unit, as filed
Floors
5
Land area
2,023 sq m
Built-up area
4,335 sq m

Timeline

RERA approvedDec 2020
Proposed completionDec 2026
TodayJul 2026
Construction progress

80% overall, as filed

Basement & plinth0%
Podiums0%
Excavation100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 40 available
BuildingFloorTypeArea sq mAvailable
ONYX13BHK1590 of 1
ONYX12BHK1150 of 2
ONYX12BHK1170 of 1
ONYX13BHK1510 of 1
ONYX12BHK1160 of 1
ONYX13BHK1570 of 1
ONYX12BHK1180 of 1
ONYX23BHK1590 of 1
ONYX22BHKmortgaged1150 of 2
ONYX23BHKmortgaged1510 of 1
ONYX22BHKmortgaged1170 of 1
ONYX22BHK1160 of 1
ONYX22BHK1180 of 1
ONYX23BHK1570 of 1
ONYX33BHK1590 of 1
ONYX32BHK1150 of 2
ONYX33BHK1510 of 1
ONYX32BHK1170 of 1
ONYX32BHK1160 of 1
ONYX33BHK1570 of 1
ONYX32BHK1180 of 1
ONYX43BHK1590 of 1
ONYX42BHK1150 of 2
ONYX43BHK1510 of 1
ONYX42BHK1170 of 1
ONYX42BHK1160 of 1
ONYX42BHK1180 of 1
ONYX43BHK1570 of 1
ONYX52BHK1180 of 1
ONYX53BHK1590 of 1
ONYX52BHK1150 of 2
ONYX53BHK1510 of 1
ONYX52BHK1170 of 1
ONYX52BHK1160 of 1
ONYX53BHK1570 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

CONCEPT DESIGN DEVELOPERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
1Projects
1Cities
2020–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KOMPALLY MUNICIPALITY
District
Medchal-Malkajgiri
Pincode
500100
North boundary
ROAD WIDTH - 9
East boundary
EXISTING BUILDING
South boundary
EXISTING BUILDING
West boundary
CTS NO
What’s nearby
Schools1 school within 500m · College or university 1.6km away
HealthcareHospital 914m away · 2 clinics within 1km
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 433m away
Getting around
Expressway 296 mPrimary road 3.8 km · Hyderabad - Karimnagar HighwayRailway line 1.3 kmRailway station 2.7km away (Gundla Pochampally)Bus stop within 500m
Water & environment
Water body 440 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 039165/MED/R1/U6/HMDSurvey no. SY NO 124 PART AND 125 PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 039165/MED/R1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.