Complete project overview

RERA Telangana · Registration filing
Units
60 units
Unit mix
40 × 2BHK, 20 × 3BHK
Saleable area
107–166 sq mper unit, as filed
Floors
5
Land area
3,048 sq m
Built-up area
11,066 sq m
Road widening
24 sq mland set aside for road widening

Timeline

RERA approvedMar 2022
Proposed completionMar 2028
TodayJul 2026
Construction progress

10% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

60 of 60 available
BuildingFloorTypeArea sq mAvailable
ORANGE ELITE13BHK1661 of 1
ORANGE ELITE12BHK1072 of 2
ORANGE ELITE12BHK1112 of 2
ORANGE ELITE12BHK1193 of 3
ORANGE ELITE12BHK1201 of 1
ORANGE ELITE13BHK1521 of 1
ORANGE ELITE13BHK1561 of 1
ORANGE ELITE13BHK1621 of 1
ORANGE ELITE22BHKmortgaged1071 of 1
ORANGE ELITE22BHK1071 of 1
ORANGE ELITE22BHKmortgaged1112 of 2
ORANGE ELITE22BHKmortgaged1192 of 2
ORANGE ELITE22BHK1191 of 1
ORANGE ELITE22BHK1201 of 1
ORANGE ELITE23BHKmortgaged1521 of 1
ORANGE ELITE23BHKmortgaged1561 of 1
ORANGE ELITE23BHKmortgaged1621 of 1
ORANGE ELITE23BHK1661 of 1
ORANGE ELITE32BHK1072 of 2
ORANGE ELITE32BHK1112 of 2
ORANGE ELITE32BHK1193 of 3
ORANGE ELITE32BHK1201 of 1
ORANGE ELITE33BHK1521 of 1
ORANGE ELITE33BHK1561 of 1
ORANGE ELITE33BHK1621 of 1
ORANGE ELITE33BHK1661 of 1
ORANGE ELITE42BHK1072 of 2
ORANGE ELITE42BHK1112 of 2
ORANGE ELITE42BHK1193 of 3
ORANGE ELITE42BHK1201 of 1
ORANGE ELITE43BHK1521 of 1
ORANGE ELITE43BHK1561 of 1
ORANGE ELITE43BHK1621 of 1
ORANGE ELITE43BHK1661 of 1
ORANGE ELITE52BHK1072 of 2
ORANGE ELITE52BHK1112 of 2
ORANGE ELITE52BHK1193 of 3
ORANGE ELITE52BHK1201 of 1
ORANGE ELITE53BHK1521 of 1
ORANGE ELITE53BHK1561 of 1
ORANGE ELITE53BHK1621 of 1
ORANGE ELITE53BHK1661 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ORANGE INFRASTRUCTURES

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
NALLAGANDLA
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500019
North boundary
4O FT ROAD
East boundary
NEIGHBOURS LAND
South boundary
NEIGHBOURS LAND
West boundary
NEIGHBOURS LAND
What’s nearby
Schools3 schools within 1km · 12 educational institutions within 1km · College or university 346m away
HealthcareHospital 592m away · Clinic within 2km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 271m away
ShoppingSupermarket 256m away · Bank 982m away · ATM within 500m
Getting around
Expressway 2.3 km · Chandanagar - RC Puram BHEL Rd Mumbai HighwayPrimary road 498 m · Nallagandla FlyoverRailway line 575 mRailway station 1.2km away (Lingampalli)Limited bus connectivity nearby
Water & environment
Water body 1.5 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C20/00215/2022Survey no. 124 PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C20/00215/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.