Complete project overview

ORERA · Registration filing
Units
84 units
Carpet area
61–90 sq mper-unit range, as filed
Building type
S+5
Parking
84 spaces
Land area
3,805 sq m
Plan valid until
28 Jul 2025
Amenities
9 filed — Water Supply, Fire Fighting Facility, Emergency Evacuation Services, Elevators, Community Center, Plantation Area/No. …
Description
(Residential Project, S+5 Residential Apartment building, No. of Units- 84)

Timeline

Construction startApr 2023
Proposed completionJul 2025
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq m
A-1011ST FLOOR89.93
A-1021ST FLOOR89.93
A-1031ST FLOOR83.98
A-1041ST FLOOR87.32
A-1051ST FLOOR84.17
A-2012ND FLOOR89.93
A-2022ND FLOOR89.93
A-2032ND FLOOR83.98
A-2042ND FLOOR87.32
A-2052ND FLOOR84.17
A-3013RD FLOOR89.93
A-3023RD FLOOR89.93
A-3033RD FLOOR83.98
A-3043RD FLOOR87.32
A-3053RD FLOOR84.17
A-4014TH FLOOR89.93
A-4024TH FLOOR89.93
A-4034TH FLOOR83.98
A-4044TH FLOOR87.32
A-4054TH FLOOR84.17
A-5015TH FLOOR89.93
A-5025TH FLOOR89.93
A-5035TH FLOOR83.98
A-5045TH FLOOR87.32
A-5055TH FLOOR84.17
B-1061ST FLOOR80.36
B-1071ST FLOOR88.72
B-1081ST FLOOR86.95
B-1091ST FLOOR61.31
B-1101ST FLOOR61.31
B-1111ST FLOOR69.58
B-1121ST FLOOR68.46
B-1131ST FLOOR61.31
B-1141ST FLOOR61.87
B-1151ST FLOOR72.46
B-1161ST FLOOR89.83
B-1171ST FLOOR80.08
B-2062ND FLOOR80.36
B-2072ND FLOOR88.72
B-2082ND FLOOR86.95
B-2092ND FLOOR61.31
B-2102ND FLOOR61.31
B-2112ND FLOOR69.58
B-2122ND FLOOR68.46
B-2132ND FLOOR61.31
B-2142ND FLOOR61.87
B-2152ND FLOOR72.46
B-2162ND FLOOR89.83
B-2172ND FLOOR80.08
B-3063RD FLOOR80.36
B-3073RD FLOOR88.72
B-3083RD FLOOR86.95
B-3093RD FLOOR61.31
B-3103RD FLOOR61.31
B-3113RD FLOOR69.58
B-3123RD FLOOR68.46
B-3133RD FLOOR61.31
B-3143RD FLOOR61.87
B-3153RD FLOOR72.46
B-3163RD FLOOR89.83
B-3173RD FLOOR80.08
B-4064TH FLOOR80.36
B-4074TH FLOOR88.72
B-4084TH FLOOR86.95
B-4094TH FLOOR61.31
B-4104TH FLOOR61.31
B-4114TH FLOOR69.58
B-4124TH FLOOR68.46
B-4134TH FLOOR61.31
B-4144TH FLOOR61.87
B-4154TH FLOOR72.46
B-4164TH FLOOR89.83
B-4174TH FLOOR80.08
B-5065TH FLOOR80.36
B-5075TH FLOOR88.72
B-5085TH FLOOR86.95
B-5095TH FLOOR61.31
B-5105TH FLOOR61.31
B-5115TH FLOOR69.58
B-5125TH FLOOR68.46
B-5135TH FLOOR61.31
B-5145TH FLOOR61.87
B-5155TH FLOOR72.46
B-5175TH FLOOR80.08

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

ORERA · Promoter registration

OMMBASTU BUILDCON PRIVATE LIMITED

Private Limited CompanyPromoter type
Khordha, OdishaBased in
1Projects
1City
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

ORERA · Registration filing
District
Khordha
Pincode
754001
What’s nearby
Schools1 school within 500m
HealthcareHospital 183m away · 9 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.6km away · Gym or sports centre 1.5km away
ShoppingSupermarket 325m away · Convenience store within 500m · Bank 805m away
Getting around
Expressway 443 m · FlyoverPrimary road 1.5 km · Nandankanan RoadRailway line 4.3 km · Howrah - Chennai Main LineRailway station 4.4km away (Bhubaneswar)Bus stop within 1km
Water & environment
Water body 1.1 km · Lily Pond
distances only — not a flood assessment
Land, title & encumbrance
Land parcels9 parcels · 3,805 sq m total
Land tenure9 of 9 parcels held under a Power of Attorney / development agreement — not a registered sale deed to the promoter
VillageBANGUARY
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

ORERA · Approved building plan

Bhubaneswar Municipal Corporation

Municipal / Corporation
Building Permit

The promised possession date (28 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhubaneswar Municipal Corporation

Municipal / Urban Local Body

Has approved 371 RERA projectsabout 1 in 3 in Odisha, more than any other body in the state.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
229
On record
22,701 flats · 11 plots
Reach
35 pincodes
Since
2019

More apartment-heavy than Odisha overall — 99% apartments here vs 87% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — ORERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — ORERA does not publish a complaints register. This read cannot speak to them either way.