Complete project overview

RERA Madhya Pradesh · Registration filing
Plots
221 plots
Unit mix
221 × Mix Size Plots
Revised completion
30 Dec 2020extended after an approved RERA extension
Extensions
3 approvedcompletion-date extension(s) granted by RERA
Quarterly reports
13 on file · latest Oct 2017 - Dec 2017quarterly progress certificates filed with RERA

Timeline

Project startedJan 2017
RERA registeredOct 2019
Proposed completionDec 2019
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

221 plots across 1 batch
TypeArea sq mCount
Mix Size Plots221

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

PRUFINE SOLUTION

Partnership Firm / LLPPromoter type
1Projects
1City
2019–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Madhya Pradesh · Registration filing
District
Dewas
Tehsil
Dewas
Planning area
Other
Address
KH. NO. 76/4, DISTRICT DEWAS
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 334m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 127m away · Bank 199m away
Getting around
Expressway 3.0 km · Dewas BypassPrimary road 3 mRailway line 808 mRailway station 1.2km away (Dewas Junction)Limited bus connectivity nearby
Water & environment
Water body 1.6 km
distances only — not a flood assessment
04

Planning authority

RERA Madhya Pradesh · Approved building plan
Layout Permit

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.