Complete project overview

RAJ-RERA · Registration filing
Plots
76 plots
Land area
19,100 sq m
Completion deadline extended
1 extension on record — latest to 28 Aug 2026declared reason: other than force majeure
Description
1). As per Township Policy 2010, 12 Plots (Plot No. 48 to 53 and 58 to 63) having Total area of 1152.42Sq. Mtrs equal to 12.5% of saleable area have been kept as mortgage under KDA Kota. These plots would be allotted after the internal development work of project is completed and development charges are deposited with KDA Kota. 2). Since it is a plotted development project therefore no parking details are required. 3. The Total Open Area 10466.17 Square meters and the area related with Park/SW/MT 1022.30 Sq Mtr, Road 9443.87 Sq Mtr.

Timeline

Construction startSep 2024
RERA registeredOct 2024
Proposed completionFeb 2026
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

76 plots across 19 batches
TypeArea sq mCount
Plot9310
Plot1122
Plot2631
Plot1341
Plot13918
Plot1672
Plot2681
Plot9328
Plot1123
Plot1001
Plot1151
Plot1971
Plot2011
Plot1251
Plot981
Plot731
Plot861
Plot1001
Plot1131

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

PRANATI BUILDCON

OrganisationPromoter type
Kota, RajasthanBased in
10Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
732 plotson the public record across 10 projects
41,468 sq mbuilt-up filed
1,56,300 sq mplotted area
1,65,806 sq mland declared
₹134.66 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Urban Improvement TrustUrban Improvement Trust6 of 7 projects
Kota Development AuthorityUrban Development Authority1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
105, 106, 107, Naya Khera, Ladpura, Kota, 324008
Village
Naya Khera
Taluka
Ladpura
District
Kota
Pincode
324008
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.6km away
LifestylePark 1.6km away
ShoppingNo supermarket within 2km
Getting around
Primary road 619 m · patan RoadRailway line 592 mRailway station 4.6km away (Tirath)Limited bus connectivity nearby
Water & environment
Canal 579 mRiver 2.1 km · Chambal River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.88 Cr declared to build 76 plots. What that works out to:

₹7.74 Lakhdeclared cost per plotall-in — land + construction
₹286/sq ftof plotted area₹3,081/sq m
49%of the cost is land₹140/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Layout Permitapproved 17 Oct 2024 · 1 yr ago

The promised possession date (28 Feb 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.