01

Complete project overview

RAJ-RERA · Registration filing
Land area
14,283 sq m
Completion deadline extended
2 extensions on record — latest to 31 Mar 2022declared reason: force majeure

Timeline

Construction startMar 2016
RERA registeredNov 2017
Proposed completionMar 2020
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

SNG REALESTATE PRIVATE LIMITED

OrganisationPromoter type
Churu, RajasthanBased in
6Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,016 homeson the public record across 6 projects
89,220 sq mbuilt-up filed
73,815 sq mplotted area
1,06,351 sq mland declared
₹171.80 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nagar ParishadMunicipal Council1 of 2 projects
Urban Improvement TrustUrban Improvement Trustthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SNG REALESTATE PRIVATE LIMITED— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
791/100, Ramsara Road, Churu, Churu, 331001
Taluka
Churu
District
Churu
Pincode
331001
What’s nearby
SchoolsNo schools within 2km · College or university 1.3km away · Library 1.6km away
HealthcareHospital 1.5km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.2 kmPrimary road 1.2 kmRailway line 1.1 kmRailway station 1.2km away (Churu Junction)Limited bus connectivity nearby
Water & environment
Water body 3.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.01 Cr declared. What that works out to:

16%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Building Permitapproved 17 Nov 2017 · 8 yrs ago

The promised possession date (31 Mar 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RAJ-RERA

07

Other projects nearby

The register · within Churu

One residential project still under way within Churu. The nearest 1:

Of the 5 projects the radar draws within 6 km — every kind, every stage — none is a residential project still under way. This list keeps only those, and looks further out.

SujangarhMixed (Residential And Commercial)

CITY CENTRE

KRA ANEKANT PRIVATE LIMITED

Mar 2024registered
Nov 2026target completion
Declared cost₹24.00 CrScale318 flatsAuthorityRAJ-RERA

Projects within Churu, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.