HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Towers
7
Land area
9,109 sq m
FAR sanctioned
2.25
Covered area
2,911 sq m
Open area
6,198 sq m

Timeline

Project startedJan 2014
RERA registeredOct 2019
Proposed completionFeb 2024
TodayJul 2026
Construction progress

70% overall, as filed

Amenities11%
External infra17%
Internal infra22%
Finishing36%
Common areas48%
Super-structure61%
Sub-structure100%
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Karnataka · Promoter registration

PARTH CONSTRUCTIONS PVT LTD

Bengaluru UrbanBased in
1Projects
1City
2019–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru North
District
Bengaluru Urban
Address
164/1 kodigehalli thindlu main road, virupakshpura, after kodigehalli railway underpass
What’s nearby
Schools1 school within 1km · College or university 1.7km away · Library 1.9km away
HealthcareHospital 1.2km away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 950m away
ShoppingSupermarket 171m away · Bank 166m away · ATM within 500m
Getting around
Expressway 1.7 kmPrimary road 2.4 km · BEL RoadRailway line 235 mRailway station 476m away (Kodigehalli)2 bus stops within 500m
Water & environment
Water body 614 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹76.25 Cr declared. What that works out to:

15%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BDA - Bangalore Development Authority

Urban Development Authority
Building Permit

The promised possession date (16 Feb 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

BDA

Urban Development Authority · Bangalore Development Authority

Has approved 830 RERA projectsabout 1 in 11 in Karnataka.

an apartments market73% apartments · 27% plotted layouts. Apartments like yours are this body's core business.

Builders
626
On record
82,843 flats · 16,515 plots
Reach
13 taluks
Since
2017

More apartment-heavy than Karnataka overall — 73% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

19 complaints on RERA Karnataka’s register for this project 2 disposed, 17 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.