Complete project overview

RERA Telangana · Registration filing
Units
144 units
Unit mix
144 × 3BHK
Saleable area
136–212 sq mper unit, as filed
Floors
8
Buildings
2
Land area
8,649 sq m
Built-up area
23,891 sq m
Road widening
1,503 sq mland set aside for road widening

Timeline

RERA approvedSep 2019
Proposed completionSep 2024
TodayJul 2026
Construction progress

30% overall, as filed

Basement & plinth0%
Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

144 of 144 available
BuildingFloorTypeArea sq mAvailable
TOWER 113BHKmortgaged1831 of 1
TOWER 113BHKmortgaged1362 of 2
TOWER 113BHKmortgaged1891 of 1
TOWER 113BHKmortgaged1612 of 2
TOWER 113BHKmortgaged1492 of 2
TOWER 123BHKmortgaged2121 of 1
TOWER 123BHKmortgaged1501 of 1
TOWER 123BHK1501 of 1
TOWER 123BHK2121 of 1
TOWER 123BHK1841 of 1
TOWER 123BHK1632 of 2
TOWER 123BHK1851 of 1
TOWER 133BHK2122 of 2
TOWER 133BHK1502 of 2
TOWER 133BHK1841 of 1
TOWER 133BHK1632 of 2
TOWER 133BHK1841 of 1
TOWER 143BHK2122 of 2
TOWER 143BHK1502 of 2
TOWER 143BHK1841 of 1
TOWER 143BHK1632 of 2
TOWER 143BHK1841 of 1
TOWER 153BHK2122 of 2
TOWER 153BHK1502 of 2
TOWER 153BHK1841 of 1
TOWER 153BHK1632 of 2
TOWER 153BHK1841 of 1
TOWER 163BHK2122 of 2
TOWER 163BHK1502 of 2
TOWER 163BHK1841 of 1
TOWER 163BHK1632 of 2
TOWER 163BHK1841 of 1
TOWER 173BHK2122 of 2
TOWER 173BHK1502 of 2
TOWER 173BHK1841 of 1
TOWER 173BHK1632 of 2
TOWER 173BHK1841 of 1
TOWER 183BHK2122 of 2
TOWER 183BHK1502 of 2
TOWER 183BHK1841 of 1
TOWER 183BHK1632 of 2
TOWER 183BHK1841 of 1
TOWER 213BHKmortgaged1606 of 6
TOWER 213BHKmortgaged1434 of 4
TOWER 223BHK1786 of 6
TOWER 223BHK1564 of 4
TOWER 233BHK1786 of 6
TOWER 233BHK1564 of 4
TOWER 243BHK1786 of 6
TOWER 243BHK1564 of 4
TOWER 253BHK1786 of 6
TOWER 253BHK1564 of 4
TOWER 263BHK1786 of 6
TOWER 263BHK1564 of 4
TOWER 273BHK1786 of 6
TOWER 273BHK1564 of 4
TOWER 283BHK1786 of 6
TOWER 283BHK1564 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

JAGRUTHI CONSTRUCTIONS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
2Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
154 homeson the public record across 2 projects
25,145 sq mbuilt-up filed
9,095 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 2 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KOLLUR
Village
KOLLUR
Mandal
RC PURAM
District
Sangareddy
Pincode
502300
North boundary
CTS NO
East boundary
CTS NO
South boundary
CTS NO
West boundary
ROAD WIDTH 12
What’s nearby
Schools4 schools within 500m · 11 educational institutions within 1km · College or university 92m away
HealthcareHospital 157m away · 1 clinic within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Playground within 500m · Gym or sports centre 358m away
ShoppingSupermarket 1.3km away · Mall 626m away · Bank 44m away
Getting around
Expressway 55 mRailway line 2.4 kmRailway station 2.6km away (Ramachandrapuram TS)Bus stop within 500m
Water & environment
Water body 694 m · PATANCHERU CHERUVU
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Rainwater20%
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 193/E/4,193/E/5,193/E/6,193/E/7,193/E/8,193/E/9,193/E/10,193/E/11,193/E/12,193/E/13,193/E/14,193/E/15,193/E/16

The promised possession date (14 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.