HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
40 units
Unit mix
20 × 3BHK, 20 × 2BHK
Saleable area
103–150 sq mper unit, as filed
Floors
5
Land area
2,142 sq m
Built-up area
4,493 sq m
Road widening
4 sq mland set aside for road widening

Timeline

RERA approvedMar 2021
Proposed completionMar 2027
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

40 of 40 available
BuildingFloorTypeArea sq mAvailable
Prems Sai Serene13BHKmortgaged1501 of 1
Prems Sai Serene13BHKmortgaged1491 of 1
Prems Sai Serene12BHKmortgaged1111 of 1
Prems Sai Serene12BHKmortgaged1051 of 1
Prems Sai Serene13BHK1491 of 1
Prems Sai Serene13BHK1421 of 1
Prems Sai Serene12BHK1031 of 1
Prems Sai Serene12BHKmortgaged1031 of 1
Prems Sai Serene23BHK1501 of 1
Prems Sai Serene23BHK1492 of 2
Prems Sai Serene22BHK1111 of 1
Prems Sai Serene22BHK1051 of 1
Prems Sai Serene23BHK1421 of 1
Prems Sai Serene22BHK1032 of 2
Prems Sai Serene33BHK1501 of 1
Prems Sai Serene33BHK1492 of 2
Prems Sai Serene32BHK1111 of 1
Prems Sai Serene32BHK1051 of 1
Prems Sai Serene33BHK1421 of 1
Prems Sai Serene32BHK1032 of 2
Prems Sai Serene43BHK1501 of 1
Prems Sai Serene43BHK1492 of 2
Prems Sai Serene42BHK1111 of 1
Prems Sai Serene42BHK1051 of 1
Prems Sai Serene43BHK1421 of 1
Prems Sai Serene42BHK1032 of 2
Prems Sai Serene53BHK1501 of 1
Prems Sai Serene53BHK1492 of 2
Prems Sai Serene52BHK1111 of 1
Prems Sai Serene52BHK1051 of 1
Prems Sai Serene53BHK1421 of 1
Prems Sai Serene52BHK1032 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

PREM CONSTRUCTIONS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
5Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
142 homeson the public record across 5 projects
16,094 sq mbuilt-up filed
7,687 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project3 of 4 projects
Pune Municipal CorporationMunicipal Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Hafeezpet
Village
Old Hafeezpet
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500049
North boundary
Neighbours Land
East boundary
Neighbours Land
South boundary
Neighbours Land
West boundary
9 mts road
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km
HealthcareHospital 814m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 650m away · Gym or sports centre 733m away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 755m away · Bank 777m away
Getting around
Expressway 839 m · Miyapur - Allwyn Cross Road Mumbai HighwayPrimary road 126 m · Gachibowli - Miyapur Road Mumbai HighwayRailway line 568 mRailway station 834m away (Hafeezpet)Bus stop within 1km
Water & environment
Water body 425 m · Kotha Kunta
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C21/04977/2021Survey no. 54
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C21/04977/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.