Complete project overview

RERA Telangana · Registration filing
Units
70 units
Unit mix
60 × 2BHK, 10 × 3BHK
Saleable area
102–136 sq mper unit, as filed
Floors
5
Land area
3,341 sq m
Built-up area
6,920 sq m

Timeline

RERA approvedNov 2021
Proposed completionNov 2027
TodayJul 2026
Construction progress

96% overall, as filed

Flat fit-out90%
Stairs & lifts90%
External finishes90%
OC-readiness90%
Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

35 of 70 available
BuildingFloorTypeArea sq mAvailable
PUPPALAS SUNSHINE13BHK1210 of 1
PUPPALAS SUNSHINE13BHK1361 of 1
PUPPALAS SUNSHINE12BHK1026 of 12
PUPPALAS SUNSHINE23BHKmortgaged1211 of 1
PUPPALAS SUNSHINE22BHKmortgaged1025 of 10
PUPPALAS SUNSHINE22BHK1021 of 2
PUPPALAS SUNSHINE23BHKmortgaged1360 of 1
PUPPALAS SUNSHINE33BHK1361 of 1
PUPPALAS SUNSHINE32BHK1026 of 12
PUPPALAS SUNSHINE33BHK1210 of 1
PUPPALAS SUNSHINE43BHK1361 of 1
PUPPALAS SUNSHINE42BHK1026 of 12
PUPPALAS SUNSHINE43BHK1210 of 1
PUPPALAS SUNSHINE53BHK1361 of 1
PUPPALAS SUNSHINE52BHK1026 of 12
PUPPALAS SUNSHINE53BHK1210 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MS INFRACON

PartnershipPromoter type
Warangal Urban, TelanganaBased in
1Projects
1City
2021–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Rangshaipet
Village
Rangshaipet
Mandal
Khila Warangal
District
Warangal Urban
Pincode
506001
North boundary
30 feet wide road land of g srinath and harinath
East boundary
property of K Yoganand and others
South boundary
100 feet wide ROB link road to khammam and others
West boundary
land of puppala kailasam and others
What’s nearby
Schools1 school within 1km · 3 educational institutions within 1km · College or university 970m away
HealthcareHospital 398m away · 2 clinics within 1km
LifestylePark 1.8km away
ShoppingNo supermarket within 2km · Bank 859m away
Getting around
Expressway 161 mRailway line 3.2 kmRailway station 3.2km away (Warangal)Limited bus connectivity nearbyAirport 3.6km away
Water & environment
Water body 845 m
distances only — not a flood assessment
Declared external development
Rainwater90%
Water supply90%
Sewerage (Chamber,…90%
Green Strip/TOT LO…90%
Solid waste0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3006/33267/W1/2021Survey no. 37/1/1 31/1/1/2 31/1/1/1/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3006/33267/W1/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.