HORIZONMarkets
01

Complete project overview

WBRERA · Registration filing
Apartments
14
Commercial units
13
Land area
512 sq m
Built-up area
1,085 sq m
Carpet area
984 sq m
Parking
6 spaces
RERA registered
2025

Timeline

RERA registeredJan 2025
Proposed completionNov 2026
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

R.P.CONSTRUCTION

Partnership FirmPromoter type
South 24-Parganas, West BengalBased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
South 24-Parganas
Municipality / area
Sonarpur
Police station
Sonarpur
Address
Mouza Sonarpur, LR Dag no. 436, 439 and 440 under LR Khatian nos.6958, 5461, 4467, 5460, 5619 and 5408, JL no.39 Ward 13 of the Rajpur Sonarpur Municipality, Road Saheb Para, Holding no. 279
Pincode
700150
What’s nearby
Schools2 schools within 1km · College or university 1.1km away
HealthcareHospital 386m away · Pharmacy within 1km
LifestylePark 1.5km away · Gym or sports centre 1.2km away
ShoppingSupermarket 1.1km away · Mall 1.9km away · Convenience store within 500m
Getting around
Primary road 368 m · Garia Main RoadRailway line 1.8 km · Sealdah-NamkhanaMetro station 667m away (Kavi Nazrul)Limited bus connectivity nearby
Water & environment
River 475 m · Adi GangaWater body 477 m
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Rajpur-Sonarpur Municipality

Municipality
Building Permit no. SWS-OBPAS/2207/2024/1814
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan SWS-OBPAS/2207/2024/1814 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Rajpur-Sonarpur Municipality

Municipal corporation / municipality

Has approved 210 RERA projectsabout 1 in 12 in West Bengal.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
156
On record
6,590 flats · 0 plots

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.