Complete project overview

RERA Chhattisgarh · Registration filing
Quarterly reports
13 on filequarterly progress reports filed with RERA

Timeline

RERA registeredOct 2018
Proposed completionApr 2024
TodayJul 2026
Construction progress

61% overall, as filed

Landscaping And Tree Planting0%
Solid Waste Management And Disposal0%
Water Supply20%
Internal Roads And Footpaths50%
Energy Maanagement65%
Storm Water Drains85%
Street Lighting90%
From the promoter's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Chhattisgarh · Promoter registration

PRESIDENT, RAJENDRA NAGAR GRIHA NIRMAN SAMITI MARYADIT

Government/Semi Government AgencyPromoter type
1Projects
1City
2018–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Bastar
Tehsil
Jagdalpur
Address
VILLAGE - KANGOLI, LOKMANYA TILAK WARD, JAGDALPUR BASTAR (C.G.)
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 840m away · 3 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 398m away
Getting around
Expressway 2.0 kmPrimary road 294 mRailway line 2.3 kmRailway station 3.6km away (Jagdalpur)Limited bus connectivity nearby
Water & environment
Water body 1.7 kmRiver 2.7 km · Indravati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹24.78 Cr declared. What that works out to:

89%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

Complaints register

None on record with RERA Chhattisgarh against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.