RERA Chhattisgarh · Registration filing- Quarterly reports
- 10 on filequarterly progress reports filed with RERA
Timeline
RERA registeredJul 2018
Proposed completionDec 2018
TodayJul 2026
Construction progressFrom the promoter's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
100% overall, as filed
Boundary Wall0%
Internal Roads And Footpaths100%
Water Supply100%
Sewerage100%
Storm Water Drains100%
Landscaping And Tree Planting100%
Electric Meter Room,Sub Station,Recieving Statiom100%
Treatment And Disposal Of Sewerage And Sullage Wat100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Energy Maanagement100%
Fire Protection And Fire Safety Requirements100%
Security Service100%
02
Builder’s track record
RERA Chhattisgarh · Promoter registrationRALAS INFRAVENTURES
Partnership FirmPromoter type
1Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location & price analysis
RERA Chhattisgarh · Registration filing- District
- Raipur
- Tehsil
- Raipur
- Address
- VILLAGE - DAGANIYA, RAIPUR (C.G.)
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.1km away
HealthcareHospital 194m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.4km away · Gym or sports centre 1.6km away
ShoppingSupermarket 553m away · Mall 1.8km away · Convenience store within 1km
Getting around
Expressway 736 mPrimary road 872 m · G.E. RoadRailway line 1.9 kmRailway station 1.8km away (Saraswati Nagar)Bus stop within 1km
Water & environment
Water body 325 m · Daganya Talab
distances only — not a flood assessmentPrice analysisdeclared build cost — not a sale price
₹33.46 Cr declared. What that works out to:
24%of the cost is land
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
None on record with RERA Chhattisgarh against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.