01
Complete project overview
WBRERA · Registration filing- Apartments
- 28
- Commercial units
- 4
- Land area
- 935 sq m
- Built-up area
- 2,130 sq m
- Carpet area
- 1,572 sq m
- Parking
- 20 spaces
- RERA registered
- 2024
Timeline
RERA registeredJan 2024
Proposed completionDec 2025
TodayJul 2026
02
Builder’s track record
WBRERA · Promoter registrationROYAL GROUP
Proprietorship FirmPromoter type
Kolkata, West BengalBased in
8Projects
5Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
91 homeson the public record across 8 projects
17,295 sq mbuilt-up filed
14,768 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
City and Industrial Development Corporation (CIDCO)Development Authority1 of 4 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 4 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 4 projects
Shahapur Nagar Panchayat, Shahapur, Dist ThaneMunicipal Council1 of 4 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
WBRERA · Registration filing- District
- South 24-Parganas
- Municipality / area
- Rajpur Sonarpur
- Police station
- Sonarpur
- Address
- Municipal Holding no. 92, under Ward No. 8 of Rajpur Sonarpur Municipality NA
- Pincode
- 700150
What’s nearby
Schools1 school within 1km · College or university 1.3km away
HealthcareHospital 1.1km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 515m away
Getting around
Primary road 2.3 km · Garia Main RoadRailway line 705 m · Sealdah-NamkhanaRailway station 698m away (Sonarpur Junction)Limited bus connectivity nearby
Water & environment
Water body 145 mCanal 1.9 km
distances only — not a flood assessmentCompliance & litigation recordWBRERA lists the developers it has flagged as defaulters — that line is the authority's own record; any litigation line is the promoter's own declaration at registration. A flagged line is worth verifying directly with WBRERA; none of it is a verdict on the project.
Defaulter listThis developer appears on WBRERA's defaulter list
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
- Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.