Complete project overview

RAJ-RERA · Registration filing
Plots
69 plots
Land area
15,600 sq m
Completion deadline extended
1 extension on record — latest to 31 Dec 2025declared reason: other than force majeure
Description
1.As per Township Policy 2010, 08 Plots (Plot No. 19, 35, 37, 60, 61, 62, 64, 65) having Total area of 1195.49 Sq. Mtrs equaling to 12.5% have been kept mortgage. These Plots would be allotted after the internal development work is completed and development charges are deposited with Jaipur Development Authority, Jaipur. 2. The Total Open Area 6211.95 Square meters and the area related with Park 780.03 Sqm + S.W.M 50.06 Sqm + Public Utility area 10.02Sqm + Mobile Tower Area 48.96Sqm + H.T. Line area 17.61 Sqm + ZDP Road area 881.58 Sqm + Road area 4423.69 Sqm 3. As per Township Policy 2010, 08 Plots (Plot No. 19, 35, 37, 60, 61, 62, 64, 65) having Total area of 1195.49 Sq. Mtrs equalling to 12.5% have been mortgaged now out of which 05 Plots (Plot no. 19, 35, 60, 61, 62 area is 829.27 Sq. Mtr) equalling to 10.00% are mortgage free by JDA vide letter No. JDA/DC/ZONE-12/2024/D-3223 dated 25-03-2025.

Timeline

Construction startDec 2023
RERA registeredDec 2023
Proposed completionJun 2025
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

69 plots across 43 batches
TypeArea sq mCount
Plot9312
Plot1251
Plot841
Plot1741
Plot13915
Plot1191
Plot1281
Plot2441
Plot1091
Plot2002
Plot1051
Plot1621
Plot1311
Plot1821
Plot901
Plot1151
Plot1471
Plot1331
Plot1301
Plot1581
Plot1101
Plot1291
Plot1071
Plot1581
Plot1151
Plot1361
Plot2371
Plot1061
Plot2871
Plot1421
Plot1611
Plot1301
Plot1321
Plot1551
Plot1151
Plot1151
Plot3121
Plot1141
Plot1151
Plot1191
Plot1611
Plot1581
Plot1301

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

NEW PATH DEVELOPERS LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
17Projects
2Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3,619 plotson the public record across 17 projects
779 sq mbuilt-up filed
8,81,680 sq mplotted area
8,85,352 sq mland declared
₹406.79 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Jaipur Development AuthorityDevelopment Authoritythis project5 of 7 projects
Maharashtra State Road Development Corporation2 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
692/503, 693/503, 726/504, 723/505, 725/505, 506, 508, 509, 510, 514, 699/515, 695/679, SHRIRAMGOPALPURA URF BHOJYAWAS, Sanganer, Jaipur, 302026
Village
SHRIRAMGOPALPURA URF BHOJYAWAS
Taluka
Sanganer
District
Jaipur
Pincode
302026
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.7 km · Jaipur Kishangarh ExpresswayRailway line 4.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹15.57 Cr declared to build 69 plots. What that works out to:

₹22.57 Lakhdeclared cost per plotall-in — land + construction
₹927/sq ftof plotted area₹9,981/sq m
58%of the cost is land₹540/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Layout Permitapproved 15 Dec 2023 · 2 yrs ago

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.