Complete project overview

GujRERA · Registration filing
Units
9 units
Mix
9 × Mixed Development
Carpet area
12–88 sq mper-unit range, as filed
Parking
18 spaces
Land area
341 sq m

Timeline

Project startedAug 2022
RERA registeredMar 2023
Proposed completionJun 2026
TodayJul 2026
Construction progress

81% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

9 units across 1 batch
TypeArea sq mCount
Mixed Development749

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

OM INFRASTRUCTURE

PARTNERSHIP FIRMPromoter type
Ahmedabad, GujaratBased in
9Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,378 homes · 96 plotson the public record across 9 projects
74,378 sq mbuilt-up filed
38,140 sq mland declared
₹438.26 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation3 of 9 projects
Ahmedabad Urban Development AuthorityUrban Development Authoritythis project2 of 9 projects
Gandhinagar Urban Development AuthorityUrban Development Authority1 of 9 projects
Kadi MunicipalityMunicipal / Corporation1 of 9 projects
Others1 of 9 projects
RatlamTown & Country Planning (DTCP)1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Ahmedabad City
District
Ahmedabad
Address
T.P. No. - 4 (Manipur), F. P. No. - 100/2/2, S.P. No. - 22,
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 174m away
HealthcareHospital 43m away · 12 clinics within 1km · Doctor's clinic within 1km
LifestylePark 837m away · Swimming pool within 2km
ShoppingSupermarket 1.8km away · Bank 613m away
Getting around
Primary road 668 mRailway line 603 mRailway station 734m away (Maninagar)5 bus stops within 500m
Water & environment
Water body 717 m · Kankaria LakeCanal 1.3 km · Kharicut Canal
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding to As per List · ₹51.5 Lakh outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹1.29 Cr declared to build 9 flats. What that works out to:

₹14.30 Lakhdeclared cost per flatall-in — land + construction
₹1,807/sq ftof carpet area₹19,450/sq m
72%of the cost is land₹2,507/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Ahmedabad Urban Development Authority

Urban Development Authority
Building Permitapproved 1 Mar 2023 · 3 yrs ago

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 1 block carry a Building-Use (BU) permission (latest 21 Nov 2023)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Ahmedabad Urban Development Authority

Urban Development Authority

Has approved 2,400 RERA projectsabout 1 in 7 in Gujarat.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,936
On record
3,12,468 flats · 1,153 plots
Reach
22 talukas
Since
2007

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.