Complete project overview

RAJ-RERA · Registration filing
Plots
118 plots
Land area
19,900 sq m
Completion deadline extended
3 extensions on record — latest to 15 Nov 2026declared reason: other than force majeure
Description
S.D.D.S. HOMES IS A NEW PROJECT WHICH IS PLOTTED DEVELOPMENT SCHEME APPROVED BY UIT KOTA VIDE LETTER NO. F-7/DTP/2023/908-10 DATED 06/06/2023. IT IS SITUATED AT KHASRA NO. 428 (PART), 443(PART), 444, 445, 448, 449, 450. LAND IS OWNED BY SHASHI KUMAR SHARMA, SHANTI DEVI, SUDHIR SHARMA. IT HAS TOTAL APPROVED AREA OF 19900 SQ. MTR. IN WHICH OPEN AREA IS 8179 SQ MTR & SALEABLE AREA IS 11721 SQ. MTR.. UIT KOTA HAS RESERVED 12.5% OF THE PLOTS TILL THE DEVELOPMENT & COMPLETION OF THE PROJECT. RESERVED PLOTS ARE 22-33.

Timeline

Construction startJun 2024
RERA registeredJul 2024
Proposed completionDec 2024
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

118 plots across 50 batches
TypeArea sq mCount
Plot1081
Plot701
Plot9349
Plot459
Plot1331
Plot1141
Plot1128
Plot1121
Plot1831
Plot711
Plot1371
Plot721
Plot1051
Plot631
Plot1151
Plot441
Plot531
Plot1351
Plot661
Plot1041
Plot1041
Plot1341
Plot1021
Plot1131
Plot1071
Plot1001
Plot1306
Plot721
Plot1101
Plot1121
Plot1351
Plot1331
Plot1031
Plot1131
Plot641
Plot1721
Plot821
Plot1201
Plot941
Plot1351
Plot3541
Plot1051
Plot1001
Plot1141
Plot1141
Plot1091
Plot1001
Plot1381
Plot1071
Plot1121

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SHASHI KUMAR SHARMA

IndividualPromoter type
Kota, RajasthanBased in
2Projects
1City
2024–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
187 plotson the public record across 2 projects
32,700 sq mplotted area
32,700 sq mland declared
₹16.50 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
428 (PART), 443 (PART), 444, 445, 448, 449, 450, KANSUA, KANSUA, Ladpura, Kota, 324006
Village
KANSUA
Taluka
Ladpura
District
Kota
Pincode
324006
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.5km away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.4 km · Kota BypassPrimary road 133 mRailway line 1.7 km · Mumbai - Delhi RailwayRailway station 1.8km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
River 361 mCanal 1.6 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹10.00 Cr declared to build 118 plots. What that works out to:

₹8.47 Lakhdeclared cost per plotall-in — land + construction
₹467/sq ftof plotted area₹5,025/sq m
70%of the cost is land₹327/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 19 Jul 2024 · 2 yrs ago

The promised possession date (5 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.