HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
69 units
Unit mix
36 × OTHER · 33 × SHOP
Carpet area
14–306 sq mper unit, as filed
Floors
5
Land area
1,293 sq m

Timeline

Project startedOct 2020
RERA registeredDec 2020
Proposed completionJun 2023
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

69 units across 67 batches
BuildingFloorTypeArea sq mCount
1BSMNTSHOP221
1BSMNTSHOP201
1BSMNTSHOP211
1BSMNTSHOP211
1BSMNTSHOP212
1BSMNTSHOP211
1BSMNTSHOP211
1BSMNTSHOP311
1BSMNTSHOP151
1BSMNTSHOP171
1BSMNTSHOP181
1BSMNTSHOP251
1BSMNTSHOP191
1BSMNTSHOP221
1GFSHOP841
1GFSHOP181
1GFSHOP181
1GFSHOP171
1GFSHOP151
1GFSHOP141
1GFOTHER671
11SHOP371
11SHOP241
11SHOP241
11SHOP251
11SHOP242
11SHOP251
11SHOP201
11SHOP211
11SHOP301
11SHOP221
11SHOP371
11OTHER261
11OTHER501
11OTHER161
12OTHER401
12OTHER251
12OTHER251
12OTHER251
12OTHER261
12OTHER251
12OTHER251
12OTHER251
12OTHER361
12OTHER211
12OTHER221
12OTHER181
12OTHER311
12OTHER231
12OTHER391
13OTHER401
13OTHER251
13OTHER251
13OTHER251
13OTHER261
13OTHER251
13OTHER251
13OTHER251
13OTHER361
13OTHER181
13OTHER211
13OTHER221
13OTHER311
13OTHER231
13OTHER391
14OTHER3061
15OTHER2411

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

SAI DHAM LANDMARK; NAVEEN AGARWAL; NEHA AGARWAL; NITIN AGARWAL

Partnership FirmPromoter type
1Registered projects
1Projects
1City
2020–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Prayagraj
Tehsil
Allahabad **
What’s nearby
Schools3 schools within 1km · 3 educational institutions within 1km · College or university 1.3km away
HealthcareHospital 242m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 617m away · Gym or sports centre 958m away · 47+ restaurants and cafes within 1km
ShoppingSupermarket 515m away · Bank 432m away · ATM within 500m
Getting around
Expressway 1.8 kmPrimary road 924 mRailway line 890 mRailway station 1.6km away (Allahabad City)Bus stop within 500m
Water & environment
Water body 412 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹15.71 Cr declared to build 69 flats. What that works out to:

₹22.77 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 28 Mar 2019 · 7 yrs ago
Building Permit no. 104

The promised possession date (30 Jun 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 9 Sep 2025)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan 104 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.