HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Land area
713 sq m
Covered area
399 sq m
Open area
313 sq m

Timeline

Project startedFeb 2018
RERA registeredOct 2018
Proposed completionAug 2020
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

K V V S V PRASAD

IndividualPromoter type
KarnatakaBased in
1Projects
1City
2018–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Hubballi
District
Dharwad
Pincode
560070
Address
RS NO. 111 GANGA SANGAM LAYOUT , BENGERI VILLAGE, KUSUGAL ROAD, HUBLI
What’s nearby
Schools1 school within 1km · College or university 1.4km away
HealthcareHospital 686m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 419m away
Getting around
Expressway 1.9 km · Gadag RoadPrimary road 1.0 km · Solapur RoadRailway line 1.3 kmRailway station 2.2km away (Hubballi)Bus stop within 500m
Water & environment
Water body 454 m · Nagashetty Koppa Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.10 Cr declared. What that works out to:

40%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Haveri Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (24 Aug 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Haveri Urban Development Authority

Urban Development Authority

Has approved 6 RERA projects0.1% of Karnataka.

a plotted-layout market33% apartments · 67% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
6
On record
1,112 flats · 0 plots
Reach
4 taluks
Since
2018

More layout-heavy than Karnataka overall — 67% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.