RAJ-RERA · Registration filing- Land area
- 1,00,000 sq m
- Description
- As per Township Policy 2010, 19 Plots (Plot No. 3, 39, 187, 188, 189, 190, 191, 192, 198, 202, 203, 204, 205, 215, 216, 229, 230 and RF-1, RF-2) having Total area of 6158.85 Sq. Mtrs equaling to 12.5% have been kept mortgage. These plots would be allotted after the development work is completed or development charges are deposited and occupancy certificate has been obtained from Jaipur Development Authority. And in this project Promotors owns the land comprising area 1,00,000 sq.mtrs. but due to lack of possession of land comprising area 2159.68 sq.mtr. JDA sanctioned the project only of area 97840.32 Sq.mtrs.As per remark the correct phase area has been rectified in Land Details of Registering Project.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationR D SAINI BUILDERS AND DEVELOPERS LLP
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 440, 444, 445, 446, 448, 448/496, 449, 450, 452, 443, 452, 454, 455, 496, 497, 498, 527, 824, 859, 860, 863/1, 865,, VILLAGE - MANPUR BHATAWALA AND DAYALPURA, Sanganer, Jaipur, 303905
- Taluka
- Sanganer
- District
- Jaipur
- Pincode
- 303905
₹29.43 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.