HORIZONMarkets

Timeline

Project startedAug 2015
RERA registeredDec 2017
Proposed completionAug 2018
TodayJul 2026
02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

LUCKY LAND DEVELOPERS

Partnership Firm / LLPPromoter type
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Dhar
Tehsil
Dhar
Planning area
Dhar
Address
Khasra No. 220/1/6/3, 220/1/8/1, 220/1/6/5, 220/1/6/6, 220/1/6/4, 224/1/1 Gram - Lebad Teh. & Dist. Dhar Madhya Pradesh
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 97 mPrimary road 1.3 km · Indore BypassNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 3.7 km · Chambal RiverWater body 4.0 km · Chambal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.76 Cr declared. What that works out to:

48%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Madhya Pradesh · Approved building plan

Dhar

Town & Country Planning (DTCP)
Building Permitapproved 30 Dec 2017 · 8 yrs ago

The promised possession date (3 Aug 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Dhar

Town & Country Planning area · Dhar district

Has approved 24 RERA projects0.5% of Madhya Pradesh.

a plotted-layout market13% apartments · 87% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
22
On record
322 flats · 3,034 plots
Reach
5 tehsils
Since
2017

More layout-heavy than Madhya Pradesh overall — 87% plots here vs 72% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.