HORIZON
Share

Sangwan West Avenue Apartment (LIG & EWS)

UPRERAPRJ12955 · UP-RERA · https://gethorizon.in/projects/sangwan-west-avenue-apartment-lig-and-koil-aligarh-maqwqjqc

01

Complete project overview

UP-RERA · Registration filing
Project name
Sangwan West Avenue Apartment (LIG & EWS)
Units
66 units
Unit mix
66 × 1 BHK
Carpet area
25–35 sq mper unit, as filed
Floors
3
Land area
2,641 sq m

Timeline

Project startedAug 2017
RERA registeredSep 2017
Proposed completionJan 2019
TodaySep 2026

Find your flat

Filed by floor and type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

66 units across 2 batches
BuildingFloorTypeArea sq mCount
231 BHK3524
231 BHK2542

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Builder registration

SANGWAN LANDCO PVT. LTD

CompanyPromoter type
4Registered projects
3Projects
1City
2017–2019Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
66 homes · 91 plotson the public record across 3 projects
24,050 sq mplotted area
26,691 sq mland declared
₹34.00 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SANGWAN LANDCO PVT. LTD— the full portfolio →

03

Location & price analysis

UP-RERA · Registration filing
District
Aligarh
Tehsil
Koil
Site access
As Approved by Competent Authority
What’s nearby
SchoolsNearest school 1.2km away · Library 1.3km away
HealthcareHospital 386m away · Clinic within 2km · Doctor's clinic within 1km
LifestylePark 1.1km away
ShoppingSupermarket 1.5km away · Mall 1.1km away
Getting around
Expressway 2.8 km · Aligarh BypassPrimary road 39 mRailway line 797 mRailway station 897m away (Aligarh Junction)Bus stop within 1km
Water & environment
Water body 752 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.00 Cr declared to build 66 flats. What that works out to:

₹9.09 Lakhdeclared cost per flatall-in — land + construction

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Uttar Pradesh registration department

In Uttar Pradesh it’s called the circle rate.

No government guidance rate is shown for this project.

Uttar Pradesh's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

UP-RERA · Approved building plan
approved 29 Sep 2016 · 10 yrs ago
Building Permit no. 477/15(15-16)

The promised possession date (25 Jan 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 23 Jul 2019)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan 477/15(15-16) on the approving authority’s portal to confirm the approval.

07

Other projects nearby

The register · within 25 km

7 residential projects still under way within 25 km. Step out ring by ring:

3 projects within 3 km — showing the nearest 3.

KoilResidential

SANSKAR MOON APARTMENTS

RACHANA INFRATECH; AMIT KUMAR; SMRITI COLONIZERS AND BUILDERS

Sep 2023registered
May 2026target completion
possession revisedDeclared cost₹32.00 CrScale64 flatsAuthorityUP-RERA
KoilResidential

S S Point

SEVEN HEAVEN CONSTRUCTIONS PRIVATE LIMITED

May 2023registered
Nov 2027target completion
no escrow declaredDeclared cost₹44.56 CrScale173 flatsAuthorityUP-RERA
KoilResidential

VAISHNO MANOR APARTMENT

JADON BUILDER AND DEVELOPER; FOZIA SHERWANI; GAZALA REHMAN; NADEEM KHAN; NAJEEBULLAH KHAN SHERWANI

Feb 2026registered
May 2028target completion
no escrow declaredDeclared cost₹77.47 CrScale142 flatsAuthorityUP-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.