HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Units
418 units
Mix
102 × FF AND SF 2BHK LIG (20' x 35') PLOT NO.13 TO 45, 80 TO 97 · 92 × FF AND SF LIG(20'x 40') PLOT NO.1 TO 12, 46 TO 63 71,72,75 TO 79, 98 TO 106 · 70 × FF AND SF 1BHK EWS(16' x 30')"PLOT NO. 67 TO 70, 107 TO 127, 130 TO 139 · 51 × GROUND FLOOR 2BHK LIG (20' x 35') PLOT NO.13 TO 45, 80 TO 97 · 46 × GROUND FLOOR LIG(20' x 40')"PLOT NO.1 TO 12, 46 TO 63, 71, 72,75 TO 79,98 TO 106 · 35 × GROUND FLOOR 1BHK EWS(16' x 30')"PLOT NO. 67 TO 70, 107 TO 127, 130 TO 139
Carpet area
17–159 sq mper-type range, as filed
Land area
23,136 sq m
Completion deadline extended
1 extension on record — latest to 13 Dec 2025declared reason: other than force majeure
Description
1. We have incorrectly entered Phase Area as 3,000 Sq. mtr but the correct phase area is 17361 Sq. mtr. We have previously paid the amount of Rs. 30,000 (Ref- RERA-TRANS-4573 dated 01.06.2018). Now after considering our error we have paid balance fees of Rs. 1,43,610 (Ref No.- 000173947130 dated 08.06.2018). Which makes our total payment of Rs. 1,73,610 (Rs.30,000+Rs.1,43,610) As per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

RERA registeredJul 2018
Proposed completionDec 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

418 units across 21 batches
BuildingTypeArea sq mCount
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 2BHK LIG (20' x 35') PLOT NO.13 TO 45, 80 TO 9742102
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF LIG(20'x 40') PLOT NO.1 TO 12, 46 TO 63 71,72,75 TO 79, 98 TO 1064892
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 2BHK LIG (20' x 35') PLOT NO.13 TO 45, 80 TO 974251
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS(16' x 30')"PLOT NO. 67 TO 70, 107 TO 127, 130 TO 1392770
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS PLOT NO. 64171
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR LIG(20' x 40')"PLOT NO.1 TO 12, 46 TO 63, 71, 72,75 TO 79,98 TO 1064846
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS PLOT NO. 66272
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS PLOT NO. 129231
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS(16' x 30')"PLOT NO. 67 TO 70, 107 TO 127, 130 TO 1392735
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 2BHK LIG PLOT NO. 73462
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS PLOT NO. 64172
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS PLOT NO 128272
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 2BHK LIG PLOT NO. 74432
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS PLOT NO. 66271
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS PLOT NO. 65212
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS PLOT NO. 128271
SANSKAR RESIDENCY ALWAR PHASE-IIFF AND SF 1BHK EWS PLOT NO. 129232
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 1BHK EWS PLOT NO. 65211
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 2BHK LIG PLOT NO. 73461
SANSKAR RESIDENCY ALWAR PHASE-IICOMMERCIAL C1 To C101591
SANSKAR RESIDENCY ALWAR PHASE-IIGROUND FLOOR 2BHK LIG PLOT NO. 74431

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

MGI DEVELOPERS PRIVATE LIMITED

OrganisationPromoter type
Alwar, RajasthanBased in
1Projects
1City
2018–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
323,324,325,328,329,330,331,332,333,334,335,339,340,341,342,, CHIRKHNA, CHIRKHANA, BAHADAR PUR, Alwar, 301028
Village
CHIRKHANA
Taluka
BAHADAR PUR
District
Alwar
Pincode
301028
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.3km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 834 mRailway line 2.0 kmRailway station 2.5km away (Gazika)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹24.58 Cr declared to build 418 flats. What that works out to:

₹5.88 Lakhdeclared cost per flatall-in — land + construction
₹976/sq ftof built-up area₹10,507/sq m
19%of the cost is land₹184/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 20 Jul 2018 · 8 yrs ago

The promised possession date (13 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.