Complete project overview

RERA Madhya Pradesh · Registration filing
Units
59 flats
Quarterly reports
5 on file · latest Oct 2023 - Dec 2023quarterly progress certificates filed with RERA

Timeline

Project startedOct 2023
RERA registeredApr 2024
Proposed completionNov 2024
TodayJul 2026
02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

SARDAR PATEL BUILDCON LLP

Partnership Firm / LLPPromoter type
2Projects
2Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
59 homes · 50 plotson the public record across 2 projects
₹16.15 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Ujjain
Tehsil
Ujjain
Planning area
Ujjain
Address
3/1 & 6, at Village Chandesara Teh & Dist Ujjain
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 535 mPrimary road 628 m · Dewas - Ujjain HighwayRailway line 1.1 km · DWX - UJN Rail SectionRailway station 1.6km away (Matana Buzurg)Limited bus connectivity nearby
Water & environment
River 2.5 km · SipraWater body 4.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.85 Cr declared to build 59 flats. What that works out to:

₹16.70 Lakhdeclared cost per flatall-in — land + construction
63%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Madhya Pradesh · Approved building plan

Ujjain

Town & Country Planning (DTCP)
Building Permitapproved 8 Apr 2024 · 2 yrs ago

The promised possession date (21 Nov 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ujjain

Town & Country Planning area · Ujjain district

Has approved 113 RERA projects2.1% of Madhya Pradesh.

a plotted-layout market27% apartments · 73% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
63
On record
3,543 flats · 6,346 plots
Reach
5 tehsils
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.