Complete project overview

GujRERA · Registration filing
Units
146 units
Mix
139 × 146
Carpet area
25–99 sq mper-unit range, as filed
Parking
146 spaces
Land area
3,232 sq m

Timeline

Project startedFeb 2018
RERA registeredMay 2018
Proposed completionSep 2022
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

139 units across 1 batch
TypeArea sq mCount
14648139

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

ATJ INFRASTRUCTURE

PARTNERSHIP FIRMPromoter type
Gandhinagar, GujaratBased in
2Projects
1City
2018–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
266 homeson the public record across 2 projects
17,973 sq mbuilt-up filed
6,953 sq mland declared
₹67.09 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Gandhinagar
District
Gandhinagar
Pincode
382421
Address
SARTHAK PULSE MALL, PDPU CHOKDI, BHAIJIPURA CORNER, KUDASAN
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.9 kmPrimary road 80 m · Koba - Gandhinagar HighwayMetro station 1.4km away (GNLU)Limited bus connectivity nearby
Water & environment
Water body 1.5 kmRiver 3.0 km · Sabarmati
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding to INDIA INFOLINE HOUSING FINANCE · ₹4.55 Cr outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹34.96 Cr declared to build 146 flats. What that works out to:

₹5.00 Lakh – ₹65.51 Lakhdeclared unit pricerange on the filing — not a live asking price
₹23.94 Lakhdeclared cost per flatall-in — land + construction
₹4,823/sq ftof carpet area₹51,911/sq m
24%of the cost is land₹2,458/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Gandhinagar Urban Development Authority

Urban Development Authority
Building Permitapproved 15 May 2018 · 8 yrs ago

The promised possession date (15 Sep 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 1 block carry a Building-Use (BU) permission (latest 9 Feb 2022)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Gandhinagar Urban Development Authority

Urban Development Authority

Has approved 414 RERA projects2.4% of Gujarat.

an apartments market95% apartments · 5% plotted layouts. Apartments like yours are this body's core business.

Builders
355
On record
47,140 flats · 710 plots
Reach
5 talukas
Since
2010

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.