Complete project overview

GujRERA · Registration filing
Parking
4 spaces
Land area
2,720 sq m

Timeline

Project startedJun 2014
RERA registeredFeb 2019
Proposed completionJun 2019
TodayJul 2026
Construction progress

75% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.
02

Builder’s track record

GujRERA · Promoter registration

sirajmiya kureshi

Individual/PropritorshipPromoter type
Anand, GujaratBased in
1Projects
1City
2019–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Anand
District
Anand
Pincode
388001
Address
sarvari heights, 100 feet roadindira gandhi marg, anand
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 391m away · 4 clinics within 1km
LifestylePark 1.8km away
ShoppingSupermarket 864m away · Mall 918m away
Getting around
Expressway 2.1 kmPrimary road 415 mRailway line 717 mRailway station 1.0km away (Anand Junction)Bus stop within 1km
Water & environment
Water body 925 mRiver 1.9 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.57 Cr declared. What that works out to:

210%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Anand VallabhVidhyanagar Karmsad Urban Development Authority

Urban Development Authority
Building Permitapproved 13 Feb 2019 · 7 yrs ago

The promised possession date (30 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Anand VallabhVidhyanagar Karmsad Urban Development Authority

Urban Development Authority

Has approved 167 RERA projects1% of Gujarat.

an apartments market95% apartments · 5% plotted layouts. Apartments like yours are this body's core business.

Builders
133
On record
7,710 flats · 250 plots
Since
2012

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.