01
Complete project overview
RERA Karnataka · Registration filing- Status
- Ongoing
- Plots
- 477 plots
- Land parcels
- 8 survey nos
Timeline
Proposed completionDec 2026
Construction progress53% overall, as filed
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker. UnitTypeTotal sq m
660Plot936.72
661Plot90.19
662Plot55.75
663Plot55.75
664Plot55.75
665Plot55.75
666Plot55.75
667Plot55.75
668Plot55.75
669Plot55.75
670Plot55.75
671Plot61.02
672Plot44.63
673Plot55.75
674Plot55.75
675Plot55.75
676Plot55.75
677Plot55.75
678Plot55.75
679Plot55.75
680Plot55.75
681Plot55.75
682Plot55.75
683Plot55.75
684Plot55.93
685Plot98.57
686Plot55.75
687Plot55.75
688Plot55.75
689Plot55.75
690Plot55.75
691Plot55.75
692Plot55.75
693Plot55.75
694Plot55.75
695Plot55.75
696Plot55.75
697Plot55.75
698Plot66.99
699Plot50.60
700Plot55.75
701Plot55.75
702Plot55.75
703Plot55.75
704Plot55.75
705Plot55.75
706Plot55.75
707Plot55.75
708Plot55.75
709Plot55.75
710Plot55.75
711Plot55.75
712Plot55.75
713Plot55.75
714Plot64.30
715Plot51.20
716Plot55.75
717Plot55.75
718Plot55.75
719Plot55.75
720Plot55.75
721Plot55.75
722Plot55.75
723Plot55.75
724Plot55.75
725Plot55.75
726Plot55.75
727Plot55.75
728Plot55.75
729Plot55.75
730Plot55.75
731Plot55.75
732Plot72.97
733Plot56.58
734Plot55.75
735Plot55.75
736Plot55.75
737Plot55.75
738Plot55.75
739Plot55.75
740Plot55.75
741Plot55.75
742Plot55.75
743Plot55.75
744Plot55.75
745Plot55.75
746Plot55.75
747Plot55.75
748Plot55.75
749Plot55.75
750Plot55.75
751Plot72.69
752Plot55.77
753Plot55.75
754Plot55.75
755Plot55.75
756Plot55.75
757Plot55.75
758Plot55.75
759Plot55.75
760Plot55.75
761Plot55.75
762Plot55.75
763Plot55.75
764Plot55.75
765Plot55.75
766Plot55.75
767Plot55.75
768Plot55.75
769Plot55.75
770Plot55.75
771Plot55.75
772Plot78.95
773Plot62.56
774Plot55.75
775Plot55.75
776Plot55.75
777Plot55.75
778Plot55.75
779Plot55.75
780Plot55.75
781Plot55.75
782Plot55.75
783Plot55.75
784Plot55.75
785Plot55.75
786Plot55.75
787Plot55.75
788Plot55.75
789Plot55.75
790Plot55.75
791Plot55.75
792Plot55.75
793Plot55.75
794Plot74.60
795Plot56.20
796Plot55.75
797Plot55.75
798Plot55.75
799Plot55.75
800Plot55.75
801Plot55.75
802Plot55.75
803Plot55.75
804Plot55.75
805Plot55.75
806Plot55.75
807Plot55.75
808Plot55.75
809Plot55.75
810Plot55.75
811Plot55.75
812Plot55.75
813Plot55.75
814Plot55.75
815Plot55.75
816Plot55.75
817Plot55.75
818Plot83.66
819Plot64.83
820Plot55.75
821Plot55.75
822Plot55.75
823Plot55.75
824Plot55.75
825Plot55.75
826Plot55.75
827Plot55.75
828Plot55.75
829Plot55.75
830Plot55.75
831Plot55.75
832Plot55.75
833Plot55.75
834Plot55.75
835Plot55.75
836Plot55.75
837Plot55.75
838Plot55.75
839Plot55.75
840Plot55.75
841Plot55.75
842Plot55.75
843Plot75.03
844Plot184.77
845Plot111.42
846Plot111.42
847Plot111.42
848Plot111.42
849Plot111.42
850Plot111.42
851Plot111.42
852Plot111.42
853Plot111.42
854Plot111.42
855Plot111.42
856Plot111.42
857Plot111.42
858Plot111.42
859Plot111.42
860Plot111.42
861Plot111.42
862Plot111.42
863Plot111.42
864Plot111.42
865Plot111.42
866Plot111.42
867Plot111.42
868Plot111.42
869Plot111.42
870Plot111.42
871Plot111.42
872Plot106.84
873Plot163.55
874Plot111.42
875Plot111.42
876Plot111.42
877Plot111.42
878Plot111.42
879Plot111.42
880Plot111.42
881Plot111.42
882Plot111.42
883Plot111.42
884Plot111.42
885Plot111.42
886Plot111.42
887Plot111.42
888Plot111.42
889Plot111.42
890Plot111.42
891Plot111.42
892Plot111.42
893Plot111.42
894Plot111.42
895Plot111.42
896Plot111.42
897Plot111.42
898Plot111.42
899Plot111.42
900Plot111.42
901Plot111.42
902Plot187.77
903Plot108.92
904Plot111.42
905Plot111.42
906Plot111.42
907Plot111.42
908Plot111.42
909Plot111.42
910Plot111.42
911Plot111.42
912Plot111.42
913Plot111.42
914Plot111.42
915Plot111.42
916Plot111.42
917Plot111.42
918Plot111.42
919Plot111.42
920Plot111.42
921Plot111.42
922Plot111.42
923Plot111.42
924Plot111.42
925Plot111.42
926Plot111.42
927Plot111.42
928Plot111.42
929Plot111.42
930Plot111.42
931Plot111.42
932Plot111.42
933Plot111.42
934Plot122.90
935Plot124.79
936Plot111.42
937Plot111.42
938Plot111.42
939Plot111.42
940Plot111.42
941Plot111.42
942Plot111.42
943Plot111.42
944Plot111.42
945Plot111.42
946Plot111.42
947Plot111.42
948Plot111.42
949Plot111.42
950Plot111.42
951Plot111.42
952Plot111.42
953Plot111.42
954Plot111.42
955Plot111.42
956Plot111.42
957Plot111.42
958Plot111.42
959Plot111.42
960Plot111.42
961Plot111.42
962Plot111.42
963Plot111.42
964Plot111.42
965Plot111.42
966Plot99.51
967Plot178.95
968Plot111.42
969Plot111.42
970Plot111.42
971Plot111.42
972Plot111.42
973Plot111.42
974Plot111.42
975Plot111.42
976Plot111.42
977Plot111.42
978Plot111.42
979Plot111.42
980Plot111.42
981Plot111.42
982Plot111.42
983Plot111.42
984Plot111.42
985Plot111.42
986Plot111.42
987Plot111.42
988Plot178.95
989Plot230.73
990Plot139.29
991Plot139.29
992Plot139.29
993Plot139.29
994Plot139.29
995Plot139.29
996Plot139.29
997Plot139.29
998Plot139.29
999Plot139.29
1000Plot139.29
1001Plot139.29
1002Plot139.29
1003Plot139.29
1004Plot244.59
1005Plot195.48
1006Plot111.42
1007Plot111.42
1008Plot111.42
1009Plot111.42
1010Plot111.42
1011Plot111.42
1012Plot111.42
1013Plot111.42
1014Plot111.42
1015Plot111.42
1016Plot111.42
1017Plot111.42
1018Plot111.42
1019Plot111.42
1020Plot111.42
1021Plot184.56
1022Plot55.75
1023Plot55.75
1024Plot55.75
1025Plot55.75
1026Plot55.75
1027Plot55.75
1028Plot55.75
1029Plot55.75
1030Plot55.75
1031Plot55.75
1032Plot55.75
1033Plot55.75
1034Plot55.75
1035Plot55.75
1036Plot55.75
1037Plot98.21
1038Plot98.18
1039Plot55.75
1040Plot55.75
1041Plot55.75
1042Plot55.75
1043Plot55.75
1044Plot55.75
1045Plot55.75
1046Plot55.75
1047Plot55.75
1048Plot55.75
1049Plot55.75
1050Plot55.75
1051Plot55.75
1052Plot55.75
1053Plot55.75
1054Plot55.75
1055Plot57.12
1056Plot55.75
1057Plot55.75
1058Plot55.75
1059Plot55.75
1060Plot55.75
1061Plot55.75
1062Plot55.75
1063Plot55.75
1064Plot55.75
1065Plot55.75
1066Plot55.75
1067Plot55.75
1068Plot55.75
1069Plot55.75
1070Plot55.75
1071Plot55.75
1072Plot55.75
1073Plot89.96
1074Plot89.83
1075Plot55.75
1076Plot55.75
1077Plot55.75
1078Plot55.75
1079Plot55.75
1080Plot55.75
1081Plot55.75
1082Plot55.75
1083Plot55.75
1084Plot55.75
1085Plot55.75
1086Plot55.75
1087Plot55.75
1088Plot55.75
1089Plot55.75
1090Plot55.75
1091Plot66.62
1092Plot70.27
1093Plot55.75
1094Plot55.75
1095Plot55.75
1096Plot55.75
1097Plot55.75
1098Plot55.75
1099Plot55.75
1100Plot55.75
1101Plot55.75
1102Plot55.75
1103Plot55.75
1104Plot55.75
1105Plot74.03
1106Plot139.93
1107Plot139.93
1108Plot139.93
1109Plot139.93
1110Plot139.93
1111Plot139.93
1112Plot139.93
1113Plot139.93
1114Plot139.93
1115Plot139.93
1116Plot139.93
1117Plot139.93
1118Plot139.93
1119Plot139.93
1120Plot139.93
1121Plot139.93
1122Plot139.93
1123Plot139.93
1124Plot139.93
1125Plot139.93
1126Plot139.93
1127Plot155.56
1128Plot202.25
1129Plot139.28
1130Plot139.28
1131Plot139.28
1132Plot139.28
1133Plot139.28
1134Plot139.28
1135Plot139.28
1136Plot185.01
Complete project overview — done
02
Builder’s track record
RERA Karnataka · Promoter registrationCHINNAMASTA PROPERTIES PRIVATE LIMITED
CompanyPromoter type
Bengaluru UrbanBased in
2Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
202120222023202420252026today
Builder DNAthe whole portfolio, summed
477 plotson the public record across 2 projects
1,42,044 sq mplotted area
1,42,044 sq mland declared
₹192.21 Crdeclared build cost
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
RERA Karnataka · Registration filing- Taluk
- Mandya
- District
- Mandya
- Pincode
- 571402
- Address
- Sy.No. 273, 275, 276, 277, 278 and 279 of Sathanur village; S.No.197/2, 198/1A, 198/1B, 198/2A, 198/2B, , 199/1, 199/2, 199/3, 254, 255, 256/1, 256/2, 257 of Ummadahalli Village , Mandya , Mandya, Karnataka - 571402
What’s nearbySchoolsNo schools within 2km
HealthcareHospital 1.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundExpressway 143 m · Bengaluru-Mysuru ExpresswayPrimary road 174 m · Bangalore-Mysore RoadRailway line 162 m · Mysuru–Bengaluru lineRailway station 3.5km away (Mandya)Limited bus connectivity nearby
Water & environmentRiver 1.1 km · HebballaWater body 1.2 km
distances only — not a flood assessment Land, title & encumbranceLandOwned by the promoter
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict. Price analysisdeclared build cost — not a sale price
₹88.21 Cr declared to build 477 plots. What that works out to:
₹18.49 Lakhdeclared cost per plotall-in — land + construction
62%of the cost is land
Location & price analysis — done
04
Planning authority
RERA Karnataka · Approved building planMandya Urban Development Authority
Urban Development Authorityapproved 26 Sep 2024 · 1 yr ago
Layout Permit no. MUDA/TPA/modified/residential/Sathnoor and Ummadahalli/14/2019-20Survey no. 277
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Verify it yourself — look up plan MUDA/TPA/modified/residential/Sathnoor and Ummadahalli/14/2019-20 on the approving authority’s portal to confirm the sanction.
The approving body, at scale
Mandya Urban Development Authority
Urban Development AuthorityHas approved 19 RERA projects — 0.2% of Karnataka.
a plotted-layout market — 16% apartments · 84% plotted layouts. Your plotted layout is this body's core business.
- Builders
- 19
- On record
- 88 flats · 854 plots
- Reach
- 3 taluks
- Since
- 2017
More layout-heavy than Karnataka overall — 84% plots here vs 38% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
Complaints registerNone on record with RERA Karnataka against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.