SATYAM HOMES

RAJ/P/2022/1830 · RAJ-RERA · https://gethorizon.in/projects/satyam-homes-jaipur-ttgq1ix8

01

Complete project overview

RAJ-RERA · Registration filing
Project name
SATYAM HOMES
Land area
1,191 sq m

Timeline

Construction startDec 2021
RERA registeredFeb 2022
Proposed completionDec 2024
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

SATYAM CONSTRUCTION

IndividualPromoter type
Jaipur, RajasthanBased in
5Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
165 homeson the public record across 5 projects
17,226 sq mbuilt-up filed
5,000 sq mland declared
₹26.42 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SATYAM CONSTRUCTION— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
49, 50, 51, 52, Vidhan Sabha Sachivalaya Samuh Aavasiya Yojana Vistar, Dhawas, Village - Dhawas, Jaipur, Jaipur, 302021
Village
Village - Dhawas
Taluka
Jaipur
District
Jaipur
Pincode
302021
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 739m away · 2 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.9km away
ShoppingNo supermarket within 2km · Mall 1.9km away
Getting around
Expressway 1.2 km · Jaipur Kishangarh ExpresswayPrimary road 3.3 kmRailway line 4.2 kmMetro station 3.5km away (Manasarovar)Limited bus connectivity nearby
Water & environment
Water body 2.4 km · Fountain RD
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.90 Cr declared. What that works out to:

15%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 3 Feb 2022 · 4 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

421 residential projects still under way within 25 km. Step out ring by ring:

5 projects within 1 km — showing the nearest 5.

JaipurGroup Housing

Shri Balaji Heights V

SHRI BALAJI REAL ESTATE

Apr 2025registered
Dec 2026target completion
Declared cost₹10.05 CrScale36 flatsAuthorityRAJ-RERA
JaipurGroup Housing

BALAJI IMPERIAL

BALAJI CONSTRUCTION

Aug 2026registered
Dec 2028target completion
Declared cost₹50.00 CrScale90 flatsAuthorityRAJ-RERA
JaipurGroup Housing

THE ELITE

S R Builders and Developers

Nov 2025registered
Jun 2026target completion
Declared cost₹16.00 CrScale18 flatsAuthorityRAJ-RERA
JaipurGroup Housing

SHREE RAM GREEN PARK

SHREE RAM INFRA

Mar 2025registered
Mar 2026target completion
Declared cost₹9.02 CrScale36 flatsAuthorityRAJ-RERA
JaipurGroup Housing

ASTHA EMPIRE II

ASTHA DREAM HOMES

Jul 2024registered
Dec 2027target completion
Declared cost₹11.96 CrScale42 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.