1 extension on record — latest to 12 Sep 2025declared reason: other than force majeure
Description
1) As per Township Policy 2010, 12 plots (i.e. plot no. 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47) admeasuring 970.79 Sq.M. equaling to 12.5% have been kept mortgage Jaipur Development Authority, Jaipur. These plots would be allotted after the internal development work is completed and development charges are deposited with Jaipur Development Authority, Jaipur. 2) The Total Open Area is 4249.46 Square meters consisting of Park/open area 572.56 Sq. Mtr. + Zonal Plan Road 438.72+ S.W.M. and Mobile Tower area 63.17 Sq. Mtr. + Road area 3175.01 Sq. Mtr. 3) Since it is a plotted development project there is no parking details are required.
Timeline
Construction startSep 2023
RERA registeredFeb 2024
Proposed completionSep 2024
TodaySep 2026
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
77 plots across 66 batches
TypeArea sq mCount
Plot748
Plot2791
Plot941
Plot661
Plot811
Plot912
Plot831
Plot841
Plot951
Plot731
Plot741
Plot861
Plot951
Plot891
Plot1064
Plot951
Plot951
Plot891
Plot881
Plot871
Plot931
Plot901
Plot941
Plot901
Plot961
Plot921
Plot671
Plot911
Plot951
Plot931
Plot1221
Plot1241
Plot1441
Plot911
Plot751
Plot971
Plot911
Plot941
Plot911
Plot681
Plot731
Plot911
Plot921
Plot821
Plot1351
Plot901
Plot941
Plot981
Plot951
Plot951
Plot691
Plot951
Plot931
Plot731
Plot941
Plot941
Plot951
Plot651
Plot921
Plot951
Plot941
Plot951
Plot911
Plot921
Plot1251
Plot1431
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
1382/762 and 1394/1384, MACHEDA, AMER, Jaipur, 302013
Village
MACHEDA
Taluka
AMER
District
Jaipur
Pincode
302013
What’s nearby
SchoolsNearest school 1.5km away
HealthcareHospital 1.8km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.3 km · FlyoverPrimary road 1.9 km · Sikar RoadRailway line 1.3 kmRailway station 2.4km away (Nindhar Benar)Limited bus connectivity nearby
Water & environment
Water body 2.9 km · ghodela bulding material
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹12.00 Cr declared to build 77 plots. What that works out to:
₹15.58 Lakhdeclared cost per plotall-in — land + construction
₹974/sq ftof plotted area₹10,480/sq m
83%of the cost is land₹811/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Layout Permitapproved 24 Feb 2024 · 2 yrs ago
The promised possession date (12 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Planning authority — done
06
Complaints & litigation
RAJ-RERA · public record
Complaints register
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
159 plotted projects still under way within 25 km. Step out ring by ring:
3 projects between 1 and 3 km — showing the nearest 3.