Complete project overview

GujRERA · Registration filing
Units
58 units
Mix
40 × Residential Flats Building - A - B · 2 × Residential Flats Building - B
Carpet area
83 sq mper unit, as filed
Blocks
2
Parking
4 spaces
Land area
3,541 sq m

Timeline

Project startedAug 2014
RERA registeredJan 2019
Proposed completionMar 2021
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

42 units across 2 batches
TypeArea sq mCount
Residential Flats Building - A - B8340
Residential Flats Building - B1632

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

SHILALEKH ENTERPRISE

PARTNERSHIP FIRMPromoter type
Navsari, GujaratBased in
2Projects
2Cities
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
178 homeson the public record across 2 projects
18,542 sq mbuilt-up filed
8,175 sq mland declared
₹61.24 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bilimora MunicipalityMunicipal / Corporationthis project1 of 2 projects
Surat Municipal CorporationMunicipal / Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Gandevi
District
Navsari
Pincode
396310
Address
CONVENT SCHOOL TO SOMNATH ROADNEAR CONVENT SCHOOL, GOHARBAUG, BILIMORA
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 345m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 283 mRailway line 733 mRailway station 880m away (Bilimora Junction)Limited bus connectivity nearby
Water & environment
River 452 m · KaveriWater body 2.4 kmCanal 4.1 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹10.26 Cr declared to build 58 flats. What that works out to:

₹22.00 Lakh – ₹44.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹17.70 Lakhdeclared cost per flatall-in — land + construction
₹1,976/sq ftof carpet area₹21,264/sq m
12%of the cost is land₹332/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Bilimora Municipality

Municipal / Corporation
Building Permitapproved 4 Jan 2019 · 7 yrs ago

The promised possession date (31 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 2 blocks carry a Building-Use (BU) permission (latest 11 Sep 2019)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Bilimora Municipality

Municipal Corporation

Has approved 12 RERA projects0.1% of Gujarat.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
12
On record
901 flats · 0 plots
Since
2013

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.