Complete project overview
RAJ-RERA · Registration filing- Land area
- 44,544 sq m
- Description
- 1. As per Township Policy, 12.5% of Plots has been mortaged in favour of Jaipur Development Authority therefore Plot No B-10, B-11, B-12, B-13, B-14, B-15, B-16, B-43, B-44, B-45, B-59, B-97, B-98, B-99, B-100 has been mortgaged with Jaipur Development Authority. 2. As this is a Plotted Development Project therefore there is no other professional appointed and as when such professionals will be appointed then such will be intimated to RERA Authority. We have scanned the Layout plan to the best of our ability. 3. That we have not received any copy of sanctioned Layout approval letter from Jaipur Development Authority and Layout Plan is the only document received from Jaipur Development Authority. Kindly refer the terms and conditions depicted on copy of sanctioned layout plan.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationChhitar mal Meena
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 84(Village-Shree Rampura Bas Mukundpura,Tehsil-Jaipur)101,102,103,104,105,106,107,108,109,110,111,112(Village-Shree Ramgopalpura,Tehsil-Sanganer), Shree Rampura Bas Mukundpura, Shree Ramgopalpura , Sanganer, Jaipur, 302026
- Village
- Shree Rampura Bas Mukundpura, Shree Ramgopalpura
- Taluka
- Sanganer
- District
- Jaipur
- Pincode
- 302026
₹20.00 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (12 Jan 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.