Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
96 sq mper unit, as filed
Floors
5
Land area
669 sq m
Built-up area
1,638 sq m

Timeline

RERA approvedApr 2021
Proposed completionApr 2027
TodayJul 2026
Construction progress

79% overall, as filed

Basement & plinth0%
Podiums0%
OC-readiness90%
Excavation100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

14 of 20 available
BuildingFloorTypeArea sq mAvailable
SHIVANTHA SAHASRA12BHKmortgaged963 of 3
SHIVANTHA SAHASRA12BHK960 of 1
SHIVANTHA SAHASRA22BHK964 of 4
SHIVANTHA SAHASRA32BHK961 of 4
SHIVANTHA SAHASRA42BHK964 of 4
SHIVANTHA SAHASRA52BHK962 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SHIVANTHA INFRA

PartnershipPromoter type
Hyderabad, TelanganaBased in
10Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
200 homeson the public record across 10 projects
14,704 sq mbuilt-up filed
6,683 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)8 of 9 projects
TGIIC1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Pashamylaram
Village
PASHAMYLARAM
Mandal
PATANCHERU
District
Sangareddy
Pincode
502307
North boundary
Plot Nos 202 and 195
East boundary
40 Feet Wide Road
South boundary
Plot Nos 198 and 199
West boundary
40 Feet Wide Road
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.5 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.5 km
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Green Strip/TOT LO…100%
Sewage100%
Solid waste100%
Rainwater100%
Electricity90%
Roads0%
Street lighting0%
Community Building…0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan
Building Permit
Survey no. 348, 349, 350
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.