HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
2,492 sq m
Completion deadline extended
1 extension on record — latest to 31 Dec 2021declared reason: force majeure
Description
1. The name of the project has changed from "Shivgyan Casa Vista" to "Shivgyan Vivanta" on 08-07-2020 and the revised registration certificate also issued accordingly on 09-07-2020. This bears the approval of Honorable Chairman Sir. 2. W.r.t. the submitted application by the promoter details of Mr. Vinod Sawalka has removed from the promoter profile on 08-07-2020. This bears the approval of Honorable Chairman Sir. 3. Revised maps with consequent changes along with revised ATS updated on 22.12.2020. This bears the approval of Honorable Chairman Sir. 4.As per applicant request application to update/delete Project Litigation details and further to the approval of Hon'ble Chairman on 13-01-2021, Project Litigation details were deleted/removed from the online portal of the said Project on 15-01-2021.

Timeline

Construction startJan 2015
RERA registeredNov 2017
Proposed completionDec 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Shivgyan Developers Private Limited

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
122, 123, 124, 166 & 167, 160 ft Road, Sawaigator, Opp. Airport Terminal 2, Near Jawahar Circle, Sanganer, Sanganer, Jaipur, 302017
Village
Sanganer
Taluka
Sanganer
District
Jaipur
Pincode
302017
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.5km away · Mall 1.3km away
Getting around
Expressway 1.4 kmPrimary road 764 m · Tonk RoadRailway line 1.9 km · Jaipur to Sawai Madhopur LineRailway station 3.1km away (Durgapura)2 bus stops within 500m
Land, title & encumbrance
Litigation4 cases on record — Civil Writs (2015)
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹56.54 Cr declared. What that works out to:

40%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 9 Nov 2017 · 8 yrs ago

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.