RERA Chhattisgarh · Registration filing
Units
1 units
Quarterly reports
9 on filequarterly progress reports filed with RERA

Timeline

RERA registeredApr 2019
Proposed completionDec 2019
TodayJul 2026
Construction progress

100% overall, as filed

Internal Roads And Footpaths100%
Water Supply100%
Sewerage100%
Storm Water Drains100%
Landscaping And Tree Planting100%
Street Lighting100%
Electric Meter Room,Sub Station,Recieving Statiom100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Energy Maanagement100%
Fire Protection And Fire Safety Requirements100%
Boundary Wall100%
Security Service100%
Lift100%
From the promoter's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Chhattisgarh · Promoter registration

SANTOSH SONI

IndividualPromoter type
1Projects
1City
2019–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Durg
Tehsil
Durg
Address
VILLAGE -KATULBOD,TEHSIL-DUGR,DIST-DURG
What’s nearby
SchoolsNearest school 2.0km away · College or university 972m away · Library 1.7km away
HealthcareHospital 345m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.6km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 1.0 kmPrimary road 695 mRailway line 677 mRailway station 1.3km away (Durg Junction)Limited bus connectivity nearby
Water & environment
Water body 531 mCanal 821 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.16 Cr declared to build 1 flat. What that works out to:

₹3.16 Crdeclared cost per flatall-in — land + construction
8%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

Complaints register

None on record with RERA Chhattisgarh against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.