Complete project overview

RAJ-RERA · Registration filing
Units
399 units
Mix
29 × LIG (BLOCK C) Fifth FLOOR FLAT NO. 1 TO 21, 22 TO 29 · 29 × LIG (BLOCK C) seventh FLOOR FLAT NO. 1 TO 21, 22 TO 29 · 29 × LIG (BLOCK C) first FLOOR FLAT NO. 1 to 21, 22 to 29 · 29 × LIG (BLOCK C) sixth FLOOR FLAT NO. 1 TO 21, 22 TO 29 · 29 × LIG (BLOCK C) third FLOOR FLAT NO. 1 TO 21, 22 TO 29 · 29 × LIG (BLOCK C) second FLOOR FLAT NO. 1 TO 21, 22 TO 29
Carpet area
9–42 sq mper-type range, as filed
Land area
22,098 sq m
Completion deadline extended
3 extensions on record — latest to 30 Jun 2027declared reason: other than force majeure
Description
The promoter is in the process of filing for revision of the maps of the project which shall be done in due course of time as per the applicable laws. The following details have been submitted by the developers After receiving the revised maps have been approved by JDA. The details of previous approved & revised approval is as follows: Block -A Previously approved maps(G+4) Revised approved maps(G+7) LIG Apartments 220 247 Two Wheeler Parking 440 494 Block -B Previously approved maps(G+4) Revised approved maps(G+7) LIG Apartments 355 499 Two Wheeler Parking 710 998 Block -C Previously approved maps(G+4) Revised approved maps(G+7) LIG Apartments 195 164 EWS Apartments 0 256 Two Wheeler Parking 390 584 Block -D Previously approved maps(G+4) Revised approved maps EWS Apartments 315 removed Two Wheeler Par 630 removed The maps approved on Dated 24.07.2017 Have been attetched with approved letter under copy of layout approval and building plan approval. The Revised maps approved on Dated 27.10.2017 Have been attetched with approved letter under Other approval as may be required and obtained for the project. The above mentioned details are being added on 27.02.2018 As per applicant request application & further to the approval and order of Hon'able chairman,on 19/03/2020 Project status change from New to Ongoing Project,and same has been updated on 05/05/2020 As per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

RERA registeredSep 2017
Proposed completionJun 2022
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

399 units across 26 batches
BuildingTypeArea sq mCount
SHREE AASHRYA GOLDEWS (BLOCK C) fifth floor flat no. 1 to 7, 12, 18 to 21, 26 to 322519
SHREE AASHRYA GOLDLIG (Block C) Ground Floor flat no. 1 to 17, 22 to 294225
SHREE AASHRYA GOLDEWS (Block C) Ground Floor Flat No. 1 to 4, 6,7,12,20,21,27 to 302513
SHREE AASHRYA GOLDEWS (BLOCK C) fourth FLOOR FLAT NO. 1 to 7, 12,18 to 21,26 to 322519
SHREE AASHRYA GOLDSHOP NO. 4 (EWS)91
SHREE AASHRYA GOLDLIG (BLOCK C) Fifth FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDLIG (BLOCK C) seventh FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDEWS (BLOCK C) Second FLOOR FLAT NO. 22,23,25,28,30,32256
SHREE AASHRYA GOLDEWS (BLOCK C) sixth FLOOR FLAT NO. 1 TO 7, 12, 18 TO 21, 26 TO 322519
SHREE AASHRYA GOLDLIG (BLOCK C) first FLOOR FLAT NO. 1 to 21, 22 to 294229
SHREE AASHRYA GOLDEWS (Block C) First Floor Flat No. 1 to 3, 5,6,7,9,12,18 to 21, 26 to322519
SHREE AASHRYA GOLDLIG (BLOCK C) sixth FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDLIG (BLOCK C) third FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDLIG (BLOCK C) second FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDLIG (BLOCK C) eight FLOOR FLAT NO. 1 to 8, 13 to 214217
SHREE AASHRYA GOLDLIG (BLOCK C) fourth FLOOR FLAT NO. 1 TO 21, 22 TO 294229
SHREE AASHRYA GOLDEWS (BLOCK C) Seventh FLOOR FLAT NO. 1 TO 7, 12, 18 TO 21, 26 TO 322519
SHREE AASHRYA GOLDEWS (BLOCK C) Second FLOOR FLAT NO. 1,3 to 7, 10,11,15,16,17,19,202513
SHREE AASHRYA GOLDEWS (BLOCK C) Third floor flat no. 1 to 4, 6,7,8,10,12,16,17,19,20,25,28 to 322519
SHREE AASHRYA GOLDSHOP NO. 5 (EWS)231
SHREE AASHRYA GOLDsHOP nO. 1 (EWS)91
SHREE AASHRYA GOLDSHOP NO. 6 (LIG)351
SHREE AASHRYA GOLDSHOP NO. 7 (LIG)241
SHREE AASHRYA GOLDSHOP NO. 2 (eWS)161
SHREE AASHRYA GOLDSHOP NO. 3 (EWS)151
SHREE AASHRYA GOLDSHOP NO. 8 (LIG)401

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SHREE AASHRYA GOLD

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1230/3436,1231,1234,1234/2,1234/3, VILLAGE- NINDAR,, AMER, Jaipur, 302028
Taluka
AMER
District
Jaipur
Pincode
302028
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 782m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 822 m · Sikar RoadPrimary road 3.0 km · Jaipur RoadRailway line 4.0 kmRailway station 3.8km away (Nindhar Benar)Bus stop within 1km
Price analysisdeclared build cost — not a sale price

₹36.85 Cr declared to build 399 flats. What that works out to:

₹9.24 Lakhdeclared cost per flatall-in — land + construction
₹1,712/sq ftof built-up area₹18,429/sq m
13%of the cost is land₹204/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 27 Sep 2017 · 8 yrs ago

The promised possession date (30 Jun 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.