HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Plots
118 plots
Land area
19,597 sq m
Completion deadline extended
1 extension on record — latest to 31 Dec 2025declared reason: other than force majeure
Description
1.) 12.5% of the total saleable plots has been mortgaged by the Nagar Parishad, Sikar against the internal development work of the project those plots are plot no. 11,12,13,14,15,16,47,48,49,50,51,52,53,54,55,56 admeasuring 1810.95 sq. mtr.

Timeline

Construction startJul 2023
RERA registeredDec 2023
Proposed completionJun 2025
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

118 plots across 63 batches
TypeArea sq mCount
Plot941
Plot1331
Plot1301
Plot12813
Plot10224
Plot1321
Plot991
Plot811
Plot1121
Plot9215
Plot1121
Plot1054
Plot1981
Plot891
Plot1051
Plot1091
Plot1101
Plot934
Plot941
Plot1101
Plot1271
Plot1421
Plot1301
Plot1001
Plot1291
Plot791
Plot1441
Plot1021
Plot871
Plot1351
Plot1171
Plot811
Plot1201
Plot1301
Plot1051
Plot1281
Plot991
Plot971
Plot1231
Plot1381
Plot3281
Plot921
Plot2211
Plot1111
Plot2641
Plot721
Plot1281
Plot1291
Plot1161
Plot1251
Plot1341
Plot1481
Plot1281
Plot791
Plot1151
Plot1741
Plot1321
Plot1051
Plot1401
Plot861
Plot1371
Plot1001
Plot1451

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SHANKAR LAL BEDI

IndividualPromoter type
Sikar, RajasthanBased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
KHASRA NO. 2673/1552 & 2675/1429, RAMPURA ROAD, SIKAR, Sikar, Sikar, 332709
Village
SIKAR
Taluka
Sikar
District
Sikar
Pincode
332709
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.3 kmNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹2.79 Cr declared to build 118 plots. What that works out to:

₹2.37 Lakhdeclared cost per plotall-in — land + construction
₹132/sq ftof plotted area₹1,426/sq m
46%of the cost is land₹61/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Nagar Parishad

Municipal Council
Layout Permitapproved 28 Dec 2023 · 2 yrs ago

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal body

A Nagar Nigam / Parishad / Palika that sanctions within its own town limits. It has approved 358 RERA projects across 29 districts about 1 in 6 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.