HORIZONMarkets
01

Complete project overview

JHARERA · Registration filing
Units
11 units
Carpet area
52–97 sq mper unit, as filed
Parking
12 spaces11 covered · 1 open
Amenities declared
Road · Drinking water · Water supply · Sewage & drainage · Electricity · Fire fighting · Emergency evacuation · Solid waste · Rain-water harvesting · Renewable energy · EV charging

Timeline

Building permit grantedMay 2021
Proposed completionMay 2024
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitCarpet sq m
101 AFirst97.31
102 AFirst52.35
103 AFirst71.47
101 BSecond52.53
102 BSecond57.60
103 BSecond57.24
104 BSecond52.53
101 CThird52.53
102 CThird57.60
103 CThird57.24
104 CThird52.53

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

JHARERA · Promoter registration

TRILOKESH CONSTRUCTIONS

Partnership / LLPPromoter constitution
1Projects
1City
2021–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

JHARERA · Registration filing
District
Saraikela-Kharsawan
Circle (Anchal)
Gamharia
Village
MANJHITOLA
Address
VILL- MANJHITOLA, MOUZA- DINDLI,
Plot no.
1163
Khata no.
298
What’s nearby
Schools1 school within 1km · College or university 1.8km away · Library 1.2km away
HealthcareHospital 1.2km away · Clinic within 2km
Lifestyle1 park within 500m
ShoppingNo supermarket within 2km · Convenience store within 1km
Getting around
Expressway 1.6 kmPrimary road 2.6 km · Tata Kandra RoadRailway line 2.6 kmRailway station 3.2km away (Adityapur)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Beldih LakeRiver 1.4 km · Kharkai River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.30 Cr declared to build 11 flats. What that works out to:

₹11.82 Lakhdeclared cost per flatall-in — land + construction
₹1,827/sq ftof carpet area₹19,669/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

JHARERA · Approved building plan
Building Permitapproved 29 May 2021 · 5 yrs ago

The promised possession date (19 May 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — JHARERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — JHARERA does not publish a complaints register. This read cannot speak to them either way.