Complete project overview
RAJ-RERA · Registration filing- Land area
- 10,748 sq m
- Completion deadline extended
- 1 extension on record — latest to 30 Jul 2022declared reason: force majeure
- Description
- 1.Project is proposed under CMJAY,2015 under Provision-3B , The Typical floor plan for 1 BHK, 2BHK 3BHK including the section, elevation for all the three categories are sanctioned by the Empanelled Architect Sudhir Gautam vide letter no.-P.10(7) Navi/3/2009 Part-III dated 31.12.2018 having COA Registration No.-CA/2012/56887 having been uploaded under Building Tab-Building Sanction Plan. 2.No other professionals are appointed apart from architect and if other professionals will be appointed then such will be intimated to RERA. 3.The Finish date committed for the project as per Form"B" is 30/07/2021 which is beyond the validity period of the approved maps.The promoter takes the responsibility to obtain the necessary extention from the competent authority. 4.The Total Parking available in the project is 146 Scooter i.e 30*1(2BHK)=30 Scooter, 58*2(3BHK)=116 Scooter.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationAKB BUILDTECH LLP
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 686, KANOTA, Bassi, Jaipur, 303012
- Taluka
- Bassi
- District
- Jaipur
- Pincode
- 303012
₹12.55 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (30 Jul 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.