HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
601 sq m

Timeline

Construction startMay 2018
RERA registeredAug 2018
Proposed completionDec 2019
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

SHRI NANDINI COMPLEX

OrganisationPromoter type
Bharatpur, RajasthanBased in
1Projects
1City
2018–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Kotwali to Kumher Gate Road, Ward No. - 29, Near City Kotwali, Kotwali to Kumher Gate Road, Near Bharatpur City Kotwali, Bharatpur City, Bharatpur, Bharatpur, 321001
Village
Bharatpur City
Taluka
Bharatpur
District
Bharatpur
Pincode
321001
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 57m away · 5 clinics within 1km · Doctor's clinic within 1km
Lifestyle6 parks within 500m · 13+ restaurants and cafes within 1km
ShoppingSupermarket 114m away · Bank 218m away · ATM within 500m
Getting around
Expressway 2.2 km · Agra Jaipur Bikaner RoadPrimary road 552 mRailway line 2.1 km · Bharatpur - BandikuiRailway station 2.2km away (Bharatpur Junction)Bus stop within 1km
Water & environment
Canal 495 mWater body 514 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹1.67 Cr declared. What that works out to:

16%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Municipal Corporation

Municipal Corporation
Building Permitapproved 10 Aug 2018 · 7 yrs ago

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal body

A Nagar Nigam / Parishad / Palika that sanctions within its own town limits. It has approved 358 RERA projects across 29 districts about 1 in 6 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.