HORIZONMarkets
01

Complete project overview

RERA Madhya Pradesh · Registration filing
Plots
28 plots
Quarterly reports
3 on file · latest Jul 2025 - Sep 2025quarterly progress certificates filed with RERA

Timeline

Project startedJun 2025
RERA registeredSep 2025
Proposed completionJun 2029
TodayJul 2026
02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

SHRI SAWARIYA INFRATECH

Partnership Firm / LLPPromoter type
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Madhya Pradesh · Registration filing
District
Narmadapuram
Tehsil
Narmadapuram Nagar
Planning area
Narmadapuram
Address
Village- Kishanpur, Tehsil Narmadapuram Nagar, District Narmadapuram, M.P.
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
No metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 3.9 km · Palakmati River
distances only — not a flood assessment
04

Planning authority

RERA Madhya Pradesh · Approved building plan

Narmadapuram

Town & Country Planning (DTCP)
Layout Permitapproved 24 Sep 2025 · 10 mo ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Narmadapuram

Town & Country Planning area · Narmadapuram district

Has approved 107 RERA projects2% of Madhya Pradesh.

a plotted-layout market11% apartments · 89% plotted layouts. Your plotted layout is this body's core business.

Builders
84
On record
788 flats · 10,849 plots
Reach
7 tehsils
Since
2017

More layout-heavy than Madhya Pradesh overall — 89% plots here vs 72% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.