HORIZONMarkets
01

Complete project overview

JHARERA · Registration filing
Units
42 units
Carpet area
738–1005 sq mper unit, as filed
Parking
93 spaces93 covered · 0 open
Amenities declared
Road · Drinking water · Water supply · Sewage & drainage · Electricity · Fire fighting · Emergency evacuation · Solid waste · Rain-water harvesting · Renewable energy

Timeline

Building permit grantedDec 2020
Proposed completionDec 2023
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitCarpet sq m
AFIRST FLOOR917.61
BFIRST FLOOR738.99
CFIRST FLOOR737.59
DFIRST FLOOR968.72
EFIRST FLOOR1005.09
FFIRST FLOOR994.65
GFIRST FLOOR894.47
ASECOND FLOOR917.61
BSECOND FLOOR738.99
CSECOND FLOOR737.59
DSECOND FLOOR968.72
ESECOND FLOOR1005.09
FSECOND FLOOR994.65
GSECOND FLOOR894.47
ATHIRD FLOOR917.61
BTHIRD FLOOR738.99
CTHIRD FLOOR737.59
DTHIRD FLOOR968.72
ETHIRD FLOOR1005.09
FTHIRD FLOOR994.65
GTHIRD FLOOR894.47
AFOURTH FLOOR917.61
BFOURTH FLOOR738.99
CFOURTH FLOOR737.59
DFOURTH FLOOR968.72
EFOURTH FLOOR1005.09
FFOURTH FLOOR994.65
GFOURTH FLOOR894.47
AFIFTH FLOOR917.61
BFIFTH FLOOR738.99
CFIFTH FLOOR737.59
DFIFTH FLOOR968.72
EFIFTH FLOOR1005.09
FFIFTH FLOOR994.65
GFIFTH FLOOR894.47
ASIXTH FLOOR917.61
BSIXTH FLOOR738.99
CSIXTH FLOOR737.59
DSIXTH FLOOR968.72
ESIXTH FLOOR1005.09
FSIXTH FLOOR994.65
GSIXTH FLOOR894.65

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

JHARERA · Promoter registration

SHRISTI DEVELOPERS AND BUILDERS

Partnership / LLPPromoter constitution
3Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
122 homeson the public record across 3 projects
84,867 sq mbuilt-up filed
₹5.50 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

JHARERA · Registration filing
Address
BARA GHAGHRA, DORANDA, RANCHI, JHARKHAND,
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 2.7 kmRailway line 1.7 kmRailway station 2.0km away (Ranchi)Limited bus connectivity nearby
Water & environment
River 554 m · HarmuWater body 1.5 km
distances only — not a flood assessment
04

Planning authority

JHARERA · Approved building plan
Building Permitapproved 30 Dec 2020 · 5 yrs ago

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — JHARERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — JHARERA does not publish a complaints register. This read cannot speak to them either way.