Complete project overview

RAJ-RERA · Registration filing
Land area
10,534 sq m
Completion deadline extended
1 extension on record — latest to 5 Jul 2023declared reason: force majeure
Description
We have two plots in this projects GH - 4 & GH - 5. This project is being developed on GH -4. The GH- 5 land is proposed for future expansion. Expansion is sole discretion of the promoter, depends on market conditions. All information provided are for GH-4 Only except Total Area Of Project (In sq. meters). Following areas are limited common in this project : Parking, Store Area, Corridor & Terrace Area.

Timeline

Construction startJul 2017
RERA registeredAug 2017
Proposed completionJul 2022
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Shubh Aangan Pushp

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
GH-4, 5, PADAM VATIKA SCHEME NEAR VATIKA VILLAGE, TONK ROAD, VATIKA, Sanganer, Jaipur, 303905
Village
VATIKA
Taluka
Sanganer
District
Jaipur
Pincode
303905
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
No metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹27.66 Cr declared. What that works out to:

7%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 4 Aug 2017 · 8 yrs ago

The promised possession date (5 Jul 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.