HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
17,437 sq m
Completion deadline extended
1 extension on record — latest to 15 Aug 2021declared reason: other than force majeure
Description
1.The total number of floors in each block of this project are 10 floors (Stilt Floor, G+8). 2. The details of separate bank has been changed on 24-08-2020. The earlier account no. was 3566002100036824 of Punjab National Bank at Chetak Circle,Udaipur .3 The Development cost and Land cost has been changed on 24-08-2020,Old Development cost was 28,87,00,000/- and old Land Cost was 9,20,78,000/- 4.Architect Detail also has been modified.5.Revised Approved maps with consequent changes along with Form G updated on 24-08-2020.This bears the approval of honorable Chairman Sir.

Timeline

Construction startOct 2018
RERA registeredMar 2019
Proposed completionApr 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

SHUBH REALTY

OrganisationPromoter type
Udaipur, RajasthanBased in
6Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
295 homeson the public record across 6 projects
47,798 sq mbuilt-up filed
57,089 sq mland declared
₹79.95 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 4 projects
Bharuch- Ankleshwar Urban Development AuthorityUrban Development Authority1 of 4 projects
Pune Municipal CorporationMunicipal Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Plot No.01, Khasra no.4179,4180, UMARDA, UMARDA, Girwa, Udaipur, 313015
Village
UMARDA
Taluka
Girwa
District
Udaipur
Pincode
313015
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.5 km · Udaipur BypassPrimary road 654 mRailway line 279 mRailway station 420m away (Umra)Limited bus connectivity nearby
Water & environment
Water body 3.3 kmRiver 3.5 km · Jamri Nadi
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹20.00 Cr declared. What that works out to:

30%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 8 Mar 2019 · 7 yrs ago

The promised possession date (15 Apr 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.