HORIZONMarkets
01

Complete project overview

WBRERA · Registration filing
Apartments
63
Land area
9,775 sq m
Built-up area
9,185 sq m
Carpet area
7,242 sq m
Parking
63 spaces
RERA registered
2023

Timeline

RERA registeredJan 2023
Proposed completionJul 2025
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

SIDDHA TOWN BARUIPUR LLP

Company / LLPPromoter type
Kolkata, West BengalBased in
3Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
256 homeson the public record across 3 projects
25,322 sq mbuilt-up filed
16,944 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
South 24-Parganas
Municipality / area
Baruipur
Police station
Baruipur
Address
Gobindapur Potor More, Khasmallick Southern Bypass (E.M. Bypass Extension)
Pincode
700145
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Railway line 3.7 km · Baruipur Junction-Diamond HarbourRailway station 2.6km away (Netra)Limited bus connectivity nearby
Water & environment
River 553 mCanal 1.5 kmWater body 1.8 km
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kolkata Municipal Corporation

Municipal Corporation
Building Permit

The promised possession date (31 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kolkata Municipal Corporation

Municipal corporation / municipality

Has approved 1,030 RERA projectsabout 1 in 2 in West Bengal, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
776
On record
14,568 flats · 0 plots
Reach
5 districts

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.