Complete project overview

RAJ-RERA · Registration filing
Land area
6,549 sq m
Completion deadline extended
1 extension on record — latest to 19 Nov 2021declared reason: force majeure
Description
1. NOC FOR FIRE WILL BE UPLOADED WITH THE QUARTERLY UPDATE. 2. THERE ARE TWO MAPS APPROVED BY THE UIT UDAIPUR, AS THE OLD APPROVAL MAPS INCLUDE THE EWS/LIG AT THE SAME PROJECT LAND, WHEREAS THE NEW APPROVED MAPS ARE ONLY OF THE PROJECT & EWS/LIG HAS BEEN PROPOSED ON THE SPLIT LOCATION.AS ON DATE THE LATEST APPROVED MAPS ARE TO BE SOLELY FOLLOWED.latest approved maps from uit udaipur have been uploaded under the head of copy of layout approval & building sanction plan.3. Water supply permission is not necessary.

Timeline

Construction startOct 2014
RERA registeredOct 2017
Proposed completionNov 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Shree Ramakrishna Infraestate LLP

OrganisationPromoter type
Udaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Kh. No. 1665,1666,1668 to1676 Plot No.-1, Tekri Mali Colony, 60Ft. Road, Udaipur, Udaipur, 313001
Taluka
Udaipur
District
Udaipur
Pincode
313001
What’s nearby
SchoolsNearest school 1.4km away · Library 2.0km away
HealthcareHospital 869m away · 2 clinics within 1km
LifestylePark 1.4km away · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 861 mPrimary road 765 mRailway line 613 mRailway station 1.1km away (Udaipur City)Bus stop within 1km
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹32.26 Cr declared. What that works out to:

39%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 31 Oct 2017 · 8 yrs ago

The promised possession date (19 Nov 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.