Complete project overview

GujRERA · Registration filing
Plots
140 plots
Mix
191 × Plots
Carpet area
129–3317 sq mper-unit range, as filed
Blocks
4
Land area
50,504 sq m

Timeline

Project startedNov 2015
RERA registeredJan 2019
Proposed completionFeb 2021
TodayJul 2026
Construction progress

0% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

191 plots across 1 batch
TypeArea sq mCount
Plots177191

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

M S INFRASTRUCTURE

PARTNERSHIP FIRMPromoter type
Surat, GujaratBased in
2Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
140 plotson the public record across 2 projects
1,364 sq mbuilt-up filed
50,504 sq mplotted area
51,098 sq mland declared
₹22.61 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Jaysingpur Municipal CouncilMunicipal Council1 of 2 projects
Surat Municipal CorporationMunicipal / Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Surat City
District
Surat
Pincode
395023
Address
Block no. 288+289+307+309+343 , O.P. no. 222+223+241+243+277 T.P. S. no. 59(UNN) , At VILL - UNN , Surat
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 380m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 447 mPrimary road 2.8 kmRailway line 1.7 km · Mumbai - Delhi RailwayRailway station 1.9km away (Bhestan)Limited bus connectivity nearby
Water & environment
Water body 349 mCanal 2.7 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹22.61 Cr declared to build 140 plots. What that works out to:

₹5.99 Lakh – ₹3.32 Crdeclared unit pricerange on the filing — not a live asking price
₹16.15 Lakhdeclared cost per plotall-in — land + construction
₹416/sq ftof plotted area₹4,477/sq m
95%of the cost is land₹394/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Surat Municipal Corporation

Municipal / Corporation
Layout Permitapproved 24 Jan 2019 · 7 yrs ago

The promised possession date (28 Feb 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Surat Municipal Corporation

Municipal Corporation

Has approved 1,566 RERA projectsabout 1 in 11 in Gujarat.

an apartments market85% apartments · 15% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
1,275
On record
2,64,009 flats · 16,727 plots
Reach
8 talukas
Since
2005

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.