Complete project overview

RERA Telangana · Registration filing
Units
27 units
Unit mix
27 × 3BHK
Saleable area
196–286 sq mper unit, as filed
Floors
1
Buildings
27
Land area
8,559 sq m
Built-up area
5,837 sq m
Road widening
31 sq mland set aside for road widening

Timeline

RERA approvedJan 2019
Proposed completionJan 2024
TodayJul 2026
Construction progress

10.2% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

27 of 27 available
BuildingFloorTypeArea sq mAvailable
VILLA - 0113BHKmortgaged2191 of 1
VILLA-0213BHK2191 of 1
VILLA-0313BHK2191 of 1
VILLA-0413BHK2191 of 1
VILLA-0513BHK2111 of 1
VILLA-0613BHK2111 of 1
VILLA-0713BHK2111 of 1
VILLA-0813BHK2111 of 1
VILLA-0913BHK2191 of 1
VILLA-1013BHK2191 of 1
VILLA-1113BHK2191 of 1
VILLA-1213BHK2191 of 1
VILLA-1313BHK2111 of 1
VILLA-1413BHK2111 of 1
VILLA-1513BHK2111 of 1
VILLA-1613BHKmortgaged2161 of 1
VILLA-1713BHK2001 of 1
VILLA-1813BHK2001 of 1
VILLA-1913BHK2591 of 1
VILLA-2013BHK2861 of 1
VILLA-2113BHK2001 of 1
VILLA-2213BHK2021 of 1
VILLA-2313BHK1961 of 1
VILLA-2413BHK2121 of 1
VILLA-2513BHK2121 of 1
VILLA-2613BHK2121 of 1
VILLA-2713BHK2121 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SIRI CONSTRUCTIONS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
17Projects
5Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
237 homeson the public record across 17 projects
30,625 sq mbuilt-up filed
16,668 sq mland declared
₹24.88 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Director, Town and Country PlanningTown & Country Planning (DTCP)6 of 17 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation5 of 17 projects
Commissioner, ULBMunicipal / Corporation3 of 17 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project2 of 17 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 17 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
GOPALPUR(V),HANAMKONDA(M),WARANGAL URBAN(D).
Mandal
Hanamkonda
District
Warangal Urban
Pincode
506001
North boundary
LAND OF DAYAKAR
East boundary
LAND OF THIRUPATHI
South boundary
LAND OF VASTALA
West boundary
LAND OF SAROJA DEVI AND 30 FEET ROAD
What’s nearby
SchoolsNo schools within 2km · 4 educational institutions within 1km · College or university 861m away
HealthcareHospital 691m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 1.0km away · 6 restaurants and cafes within 1km
ShoppingSupermarket 965m away · Mall 1.0km away
Getting around
Expressway 810 mPrimary road 2.2 kmRailway line 2.9 kmRailway station 2.7km away (Komatipalli)Bus stop within 1km
Water & environment
Canal 548 mWater body 690 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit
Survey no. 22

The promised possession date (8 Jan 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.